PESHAWAR, Jan 2: Several parts of the central Hazara region will remain without electricity for 20 days due to development activities planned by the Peshawar Electric Supply Company.

According to a press release issued here on Friday, power supply through the 66kv Haripur-Hawalian-Abbottabad transmission line would remain suspended to help smooth execution of development activities.

"Power supply would remain suspended from 7am on Jan 2 to 6pm Jan 22 - for a period of 20 days - as a result of which consumers getting electricity from the 66kv Abbottabad grid station would be affected," contained the press release.

The suspension of power supply has been necessitated due to development works planned for location number 128 to 140 on the said transmission line.

Pesco, according to the release, has planned to replace the existing transmission poles with new and taller ones to elevate the electricity transmission wires in an effort to ensure maximum safety in the area.

Opinion

Editorial

Centre vs provinces
Updated 10 Jun, 2026

Centre vs provinces

The reason the centre finds itself in this position is rooted in its failure to expand the tax net and boost revenues.
Party in crisis
10 Jun, 2026

Party in crisis

THE young KP chief minister must be starting to realise just how thorny a seat he occupies. There has been a flurry...
Varsity woes
10 Jun, 2026

Varsity woes

FINANCIAL crises affecting public sector universities across Pakistan are now having an impact on academic...
Doctor attacked
09 Jun, 2026

Doctor attacked

AN act of reprehensible violence has shaken the medical community. On Saturday, an employee of the Provincial Civil...
AJK flare-up
Updated 09 Jun, 2026

AJK flare-up

The situation started deteriorating after a trader affiliated with the JAAC was reportedly shot in an altercation with law-enforcers.
Fault lines
09 Jun, 2026

Fault lines

THE April 8 ceasefire that halted hostilities between Israel and Iran has encountered its most serious test yet....