Four garbage transfer stations, landfill to be ready by August, CM Sindh told

Published
0
The Garbage Transfer Station-Imtiaz is set up along the Malir riverbank near Qayyumabad.—Shakil Adil / White Star
The Garbage Transfer Station-Imtiaz is set up along the Malir riverbank near Qayyumabad.—Shakil Adil / White Star

KARACHI: Sindh Chief Minister Syed Murad Ali Shah was informed on Thursday that infrastructure of four garbage transfer stations (GTS) and a landfill site in the metropolis would be completed by August to handle up to 7,000 tonnes of solid waste on a daily basis.

Mr Shah, who was presiding over a meeting here, was also informed that construction of the GTS was underway at Sharafi Goth, Dinga Morr, Imtiaz and Gutter Baghicha under the World Bank-funded Solid Waste Emergency & Efficiency Project (Sweep).

The GTS is a facility where solid waste collected from nearby areas is temporary stored, sorted and then loaded onto trucks for transport to landfill sites.

The meeting was told that as of February, Sharafi Goth GTS had achieved over 52 per cent physical progress, while other sites were progressing at varying stages and completion of several facilities was expected by August 2026.

According to a press statement issued by the CM House, the chief minister said Sweep was central to the vision of making Karachi a cleaner, greener and more liveable city.

He noted that the project aligned with Pakistan Vision 2025, which emphasised curbing urban pollution, modernising waste transfer systems and promoting sustainable cities.

“We are committed to providing a sustainable and liveable environment through an end-to-end, integrated solid waste management system,” the CM said, reiterating the government’s resolve to protect the city’s environment while supporting inclusive urban development.

The meeting was attended by Local Government Minister Nasir Shah, Karachi Mayor Murtaza Wahab, Chief Secretary Asif Hyder Shah, LG Secretary Waseem Shamshad and Sweep Project Director Anwar Shar.

Underlining the core objective of the project, he said it aimed to reduce Karachi’s carbon footprint while ensuring compliance with national and international environmental quality standards.

He said the project would not only modernise waste collection and disposal but also enhance safety at dumpsites, rehabilitate exhausted areas and improve living conditions and livelihoods of waste pickers residing nearby.

Regarding the landfill, the meeting was informed that development work was underway at 485-acre Jam Chakro site to build four “sanitary engineered landfills”.

Published in Dawn, February 20th, 2026

Opinion

Editorial

State of denial
Updated 18 Oct, 2026

State of denial

If the Taliban regime commits to preventing groups based on its soil from attacking neighbouring states, the process of normalisation and regional integration of Afghanistan can begin.
Suffering in silence
18 Oct, 2026

Suffering in silence

TOO many Pakistani children have nowhere to turn when abused online. An estimated 1.5m internet-using children aged...
Export imperative
18 Oct, 2026

Export imperative

THE government’s efforts to boost Pakistan’s external sector through diversified financing, higher foreign...
No talks
Updated 17 Oct, 2026

No talks

The government should understand that the PTI’s protest march and its reaction to it will look like nothing more than a storm in a teacup.
Strengthening LGs
17 Oct, 2026

Strengthening LGs

THE ECP has done well to refuse to allow the Punjab administration to push the local government elections to April....
Lesser citizens
Updated 17 Oct, 2026

Lesser citizens

Interfaith harmony will prevail when the message to end bias is conveyed from the pulpit, alongside efforts to punish zealotry.