Replacement of 16 more gates at Sukkur Barrage to begin soon: minister

Published May 12, 2025
CRANES remove silt from the riverbed before the start of gates replacement work at Sukkur Barrage.—Dawn
CRANES remove silt from the riverbed before the start of gates replacement work at Sukkur Barrage.—Dawn

SUKKUR: Sindh Minister for Irrigation Jam Khan Shoro has said that work on the replacement of 14 gates at Sukkur Barrage has been completed and now the government will begin work on 16 gates in the first phase of the project.

The minister said during a visit of the Sukkur Barrage, the North-West Canal and the Kirthar Canal in Dadu that the replacement of the gates would reduce the weight by 3,500 tonnes.

He said the work on the barrage’s infrastructure and the gates had been tested using modern machinery. The gates’ replacement work was expected to be completed by June, he said.

He stressed that there would be no compromise on the quality of the work, and all construction work must meet international standards. The Sindh government was committed to providing all necessary resources for the timely completion of the crucial projects, he said.

He expressed hope the completion of the projects would not only improve the irrigation system but also have a positive impact on Sindh’s agriculture and economy.

He directed contractors to utilise all their capabilities to complete the work within the stipulated timeframe.

The minister said in Sukkur that this project held immense importance for Sindh’s agricultural economy. Its successful completion would further help enhance the irrigation system, he said.

He instructed officials to strengthen monitoring mechanisms and promptly addressed any obstacles in the ongoing work.

Later, the minister chaired a meeting to review the ongoing work at Sukkur and Guddu barrages where discussions were held on the barrages’ rehabilitation work and the officials concerned briefed the minister on the progress of the projects.

The minister directed the officials to ensure timely completion of the work as per the approved schedule, conduct field visits regularly and monitor the progress personally.

The meeting was attended by Irrigation Secretary Zarif Khero, Pritam Das (Project Director, Sindh Barrages Improvement Project), Chief Engineers of Sukkur, Right Bank Canal, contractors and senior officials.

Published in Dawn, May 12th, 2025

Opinion

Editorial

Missing in action
17 Mar, 2026

Missing in action

NOT exactly known for playing a proactive role in protecting the interests of Muslim nations and populations...
Risk to stability
Updated 17 Mar, 2026

Risk to stability

THE risks to Pakistan’s fragile economic recovery from the US-Israel war on Iran cannot be dismissed. Yet the...
Enrolment push
17 Mar, 2026

Enrolment push

THE federal government has embarked upon the welcome initiative to enrol 25,000 out-of-school children in Islamabad...
Holding the line
16 Mar, 2026

Holding the line

PAKISTAN’S long battle against polio has recently produced encouraging signs. Data from the national eradication...
Power self-reliance
Updated 16 Mar, 2026

Power self-reliance

PAKISTAN’S transition to domestic sources of electricity is a welcome development for a country that has long been...
Looking for safety
16 Mar, 2026

Looking for safety

AS the Middle East conflict enters its third week, the war’s most enduring victims are not those who wage it....