Wapda takes stock of damage to Neelum-Jhelum dam

Published May 9, 2025
A journalist photographs the damaged wall of the Neelum-Jhelum Hydropower Project in Nausari.—AFP
A journalist photographs the damaged wall of the Neelum-Jhelum Hydropower Project in Nausari.—AFP

MUZAFFARABAD: Water and Power Development Authority (Wapda) Chairman ret­i­red Lt Gen Sajjad Ghani on Thursday visited the Neelum-Jhelum Hydropower Project (NJHP) dam site to assess damage from Indian shelling and to boost the morale of the staff deployed on-site.

The chairman was informed during a detailed inspection of the weir, de-sanders, and intake that the shelling began at 1:15am on May 7 and continued for approximately six hours, ending at 7:15am.

The bombardment damaged a hydraulic power unit of an intake gate and reinforced concrete structures at de-sanders 1 and 3. A residential camp and a medical facility, including an ambulance, were also targeted, according to officials.

Mr Ghani “strongly condemned the Indian attack on the power project,” saying international law, including an additional protocol to the Geneva Conventions of Aug 12, 1949, prohibited attacks on water infrastructure, even during full-scale wars between states.

Attack condemned as ‘act of war’; damage to systems could have triggered ‘massive flooding’

“The coward enemy’s attack is unacceptable and it will be taken up with the respective forums,” he told media at the project site. “It is an act of war which is not acceptable for Pakistan. Even in World War I, World War II and other wars, no one targeted water reservoirs, projects, etc., under norms.”

He said damage to the project’s automated systems could have caused “massive flooding from Muzaffarabad to Mangla”.

“Thank God, our project’s automated system remained safe,” he said. “And had these been affected, there would have been a flood situation from Muzaffarabad to Mangla. Our country escaped a big disaster.”

The Wapda chairman praised the project staff for their “dedication and courage” in taking timely action to protect vital installations. He was accompanied by Muham­mad Arfan Miana, acting member for power and chief executive officer of the NJHP Company, as well as the chief engineer and project director, and the chief engineer for operations and maintenance of the project.

A day earlier, ISPR Director Gen­eral Lt Gen Ahmed Sharif Chaudhry also condemned the attack, describing it as a “flagrant violation of international law and conventions”. He said targeting Pakistan’s water infrastructure “represented a dangerous escalation and posed serious humanitarian and environmental risks.”

The 969MW project completely halted power production at 6am on May 1, 2024, after its rem­a­­ining two turbines were shut down due to deteriorating conditions in its Headrace Tunnel. The first two turbines had been shut down in early April 2024 following a reduction in tunnel pressure, just days after the project had briefly achieved full generation capacity.

Khalid Hasnain in Lahore also contributed to this report

Published in Dawn, May 9th, 2025

Opinion

Editorial

Unsustainable growth
Updated 23 Jun, 2026

Unsustainable growth

CLICHÉS are an essential part of political rhetoric. But when repeated often, they lose their impact. So when...
Banned speeches
23 Jun, 2026

Banned speeches

NATIONAL Assembly Speaker Ayaz Sadiq on Sunday formally lifted long-standing restrictions on the airing of ...
New GB government
23 Jun, 2026

New GB government

WITH the newly elected lawmakers of the Gilgit-Baltistan Assembly taking oath on Monday, the PPP looks set to head...
A costly cut
Updated 22 Jun, 2026

A costly cut

Climate risks are increasing and public investment should reflect that reality.
Guarded access
22 Jun, 2026

Guarded access

ONE of the government’s ‘novel’ proposals to snag tax evaders has collided with some harsh realities. On...
Lyari’s passion
22 Jun, 2026

Lyari’s passion

THE love for football in Lyari knows no bounds. The World Cup might be underway thousands of miles away in North...