Agriculture: Lining the Nara Canal

Published February 10, 2025
WORK being carried to line the 2km stretch of Nara Canal.—Umair Ali
WORK being carried to line the 2km stretch of Nara Canal.—Umair Ali

A 2km stretch of the Nara Canal, the largest channel in Sindh’s irrigation network, has been lined to restore its original parameters, which were disturbed due to soil erosion. Nara Canal emanates from the Sukkur barrage, the oldest barrage in Sindh. The lining aims to improve water productivity in the Nara canal system that feeds the lower Sindh region and touches the desert region of Tharparkar.

From an engineering point of view, the lining was a work of important nature to ensure efficient flows with a gross cultivable area of 2.17 million acres and a cultivable command area of 2.1m acres. Nara’s main canal stretches over 226 miles, according to irrigation department figures, bringing water to major left bank districts like Sanghar, Mirpurkhas and Umerkot — a hub of mango orchards and sugarcane.

Nara Canal is part of the irrigation system managed by the Sindh Irrigation and Drainage Authority (Sida), a body that seeks to promote a participatory irrigation system. Sida has executed the project out of provincial government funding at a revised cost of Rs 4.25 billion — the project was initially planned at a cost of Rs 2.89 bn.

During the ongoing Rabi crop season, the channel was closed on Jan 6 this year ahead of the Sukkur barrage’s closure. Water supply in the canal resumed on Feb 4 with a discharge of 1,800 cusecs to enable growers to start preparing for Kharif season, which begins early in this region compared to the rest of Sindh. Depending on water availability in the Indus River, the Nara Canal can draw a maximum discharge of 18,000-19,000 cusecs, even though its designed discharge is 13,649 cusecs.

Work on the compromised canal promises improved water flow and increased capacity

“The area of the pit is located downstream between RD0+315 to RD0+955,” said Qamar Hussain, resident engineer of National Engineering Services of Pakistan (Nespak) while talking to Dawn at the site before the canal was to be opened for regular flows. Nespak was Sida’s project consultant.

According to Mr Hussain, considerable scouring occurred in the canal’s earthen bed; this lining methodology would address it now. Lining work was done between RD1+160 to RD7+050. A drainage system has been installed in the bed to protect the lined structure. Sheet piles were installed at 28ft depth inside the bed coupled with a sloppy design to help block silt upstream in the pit, he added.

Sida’s General Manager of Operations, Sajjad Soomro, observed that the sheet piles would dissipate energy in the current of water and travelling time would increase. He said the soil in the canal remained sandy as the Nara Canal used to be a natural waterway in the pre-Sukkur Barrage era. “Flows were not uniform in the canal due to pit,” he said.

Between the lined and earthen bed of the canal, a 15ft fall occurs. At this point (RD7+050), an RCC slope is added to withstand high water pressures. It is also backed by stone dumping at 250ft in length to avoid ditch formations in the bed, thus ensuring canal safety, explained executive engineer Khurram Parvez Rid.

Resultantly, the upper surface of the water at the canal head would move faster while silt-laden flows would remain trapped to cause silt deposition eventually in the same pit that is invariably 40-50ft in depth. This process would take a year or so.

The pit’s creation at Nara’s head made the canal water flow turbulent, prompting Sida to find a solution. During a rotation programme coupled with this chronic problem, water shortage complaints had increased.

Sida’s Managing Director, Pritam Das, believed that noticeable soil erosion was witnessed at a fast pace in the canal, which necessitated this work that meanders at certain locations. He pointed out that the lining would help improve efficiency in the canal’s regulations.

“Water productivity will certainly improve, and the canal will be channelised up to RD-13. The canal has witnessed major interventions and due to its capacity for carrying more water, projects like twin Jamrao were also executed,” he said. Mr Das pointed out that the lining would help restore the canal’s original parameters and address the pit issue.

Before Nara, a certain reach, around a 10km area, of Rohri canal was lined about a decade back. Rohri, being the second largest canal of Sukkur barrage, also feeds the lower Sindh districts, including Tando Allahyar, Matiari, Badin, Sukkur, etc. It was lined by the irrigation department in Benazirabad district ostensibly though to benefit a construction tycoon’s private housing scheme to control seepage in the land located adjacent to the scheme.

Nara Canal has witnessed a few essential interventions to achieve water productivity. Multibillion rupee expenditures were witnessed over the canal’s re-alignment. Construction of fall structures was another major task achieved on the canal. The Makhi Farash complex in Sanghar, Pakistan’s largest cotton-producing district, was a huge intervention.

The complex led to provisions of freshwater through Thar carrier to energy project in coal-rich Tharparkar district’s Islamkot taluka, where power generation has been taking place for the past several years to feed the national grid. Construction of the Makhi-Farash Complex has three heads and one cross regulator for the Thar, Khipro and Mithrao canals.

Three of five fall structures were built by Sida at a cost of Rs1.25 billion to remove meandering in the canal and ensure uniform flows under the World Bank-funded Water Sector Impro­vement Project through Sida.

Published in Dawn, The Business and Finance Weekly, February 10th, 2025

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Judicial disputes
Updated 23 Mar, 2025

Judicial disputes

Public perceptions of the institution’s independence and neutrality have taken a hit due to bitter, public spats between senior judges.
Biased proposal
23 Mar, 2025

Biased proposal

PAKISTAN’S tax system is extortionist, unpredictable and unsupportive of investment and economic growth. It...
JFK files
23 Mar, 2025

JFK files

THE latest cache of declassified documents from what are known as the ‘Kennedy files’ have not really impressed...
Running on empty
Updated 22 Mar, 2025

Running on empty

World Water Day should remind country’s rulers that water crisis threatens the very survival of our future generations.
Another ultimatum
22 Mar, 2025

Another ultimatum

THESE are fraught times, but the government must still find it in its heart to be a little more accommodating....
Muzzled voices
22 Mar, 2025

Muzzled voices

A NEW era of censorship is upon us. The FIA’s arrest of journalist and founder of media agency Raftar, Farhan...