ISLAMABAD: An audit of the Federal Board of Revenue (FBR) has pointed out Rs51.6 billion irregularities in a flagship project awarded to the National Logistics Cell without a tender process.

According to the audit report for the financial year 2021-22, over Rs35.08bn irregularities related to award of a contract for “Central Asia Regional Economic Cooperation, Regional Improving Border Services project for Torkham Border Crossing Point, on an engineering procurement and construction (EPC) basis, to the National Logistics Cell”.

“The FBR awarded the work directly to NLC without competitive bidding process and accepted the bid of NLC without detailed estimates and rate analysis to compare the bid rates,” the report added.

The FBR, in response to the audit objection, stated: “The project is financed by the Asian Development Bank and hence PPRA (Public Procurement Regulatory Authority) Rules are not applicable as superseded by the ADB procurement policy.”

Audit finds Torkham border crossing scheme awarded to NLC without tender

However, the Auditor General Office rejected the FBR’s reply. The audit report also pointed out that the FBR had paid a sum of Rs10.49bn to the contractor without proper verification. “Supervisory officer is required to record data-wise activity and mandatory tests at site. However, the payment for value of work was made to the contractor on account of work done without recording detailed measurement of work and prescribed checks by the engineers at various levels in support of the correctness of executed works were not exercised.”

The report also pointed out “unjustified payment” of Rs1.76bn due to inclusion of “superfluous components in the construction cost”.

As per the audit report, the FBR paid the extra amount as escalation cost without an Escalation Payment Certificate.

The audit also observed “excess payment” of Rs1.35bn which was beyond the provision of PC-1 of the project. The FBR tried to justify this with the depreciation of rupee against the dollar, but the auditors did not accept the reply and said the “expenditure has exceeded the permissible limits in different components of the project, which requires approval of the competent forum”.

The audit report termed the payment of Rs915 million to the contractor on account of provisional sum unjustified. “The amount was paid by the Project Management Unit for establishment of laboratories, shifting of utilities, environment management plan, security plan and demolition of existing building without supporting accounts, receipts, vouchers, etc,” it said.

The report said the FBR did not deduct Rs787.15m income tax from the contractor. The FBR replied that NLC has been exempted from payment of withholding income tax.

“The [FBR’s] reply was not accepted because withholding tax was included in the bid rates. Furthermore, the sub-contractors included in the contract agreement were also liable to pay the income tax,” the report observed.

According to the audit report, a sum of Rs478m paid to the contractor for security staff was also unjustified. It said the amount was paid to 124 and 146 security personnel, respective, at Torkham and Chaman borders.

“The consultant, however, reported that only 20 personnel were physically deployed on Torkham border for security, while NLC did not share any detail of personnel for both works,” the report said.

Published in Dawn, October 15th, 2022

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Editorial

Budgeting austerity
Updated 16 May, 2025

Budgeting austerity

The past policy of squeezing salaried classes and fully documented corporations to collect taxes will not work any longer.
A ‘new’ Syria
16 May, 2025

A ‘new’ Syria

THE American embrace of the post-Assad Syrian regime is complete, with President Donald Trump meeting the Arab...
Business of begging
16 May, 2025

Business of begging

IT is a matter of deep embarrassment that Pakistan has become an ‘exporter’ of beggars. Over 5,000 have been...
Rebuilding trust
Updated 15 May, 2025

Rebuilding trust

Both countries will have to restart the dialogue process. One major step India can take would be to honour the IWT.
Political off-ramp
15 May, 2025

Political off-ramp

IN the midst of every crisis, there lies great opportunity. With the nation basking in the afterglow of Pakistan’s...
Awami League ban
15 May, 2025

Awami League ban

BANGLADESH stands at a key crossroads. While the ouster of Sheikh Hasina Wajed’s government and the formation of ...