ISLAMABAD: The Pakistan Atomic Energy Commission (PAEC) on Friday announced that it had successfully connected its Karachi Nuclear Power Plant Unit-3 (K-3) to the national grid.

The 1,100-megawatts generation capacity nuclear power plant (NPP) had achieved criticality on Feb 21 and was undergoing certain safety tests and procedures before it could finally be connected to the grid.

“The plant has been connected to the grid on a testing basis and is expected to be inaugurated soon after attaining full power,” a statement said.

K-3 is the second NPP in Pakistan with the generation capacity of 1,100 MW and its addition to the national grid is expected to help reduce electricity tariff in the country, the PAEC said.

Generation capacity of PAEC-operated NPP is 1,100MW

The plants have been developed with the Chinese support.

K-3 is one of the two similar NPPs located near Karachi. The other one, named K-2, was inaugurated by Prime Minister Imran Khan on May 21 last year. The groundbreaking of both the units (K-2 & K-3) of the project was performed by then prime minister Nawaz Sharif in November 2013.

The construction of K-2 and K-3 was started in August 2015 and May 2016, respectively, after approval of the Pakistan Nuclear Regulatory Authority (PNRA). The fuel loading of the plant (K-3) started in December 2021 after getting clearance from the PNRA.

The PAEC is now running six NPPs in the country. Two of them are located in Karachi, while four in district Mianwali — Chashma Nuclear Power Plant Unit 1-4.

Earlier, the collective generation capacity of all PAEC-operated NPPs was over 2,400 MWs. The addition of K-3 in the national grid will enhance the generation capacity of nuclear power plants in the country to over 3,500MW, substantially improving the overall share of nuclear power in the energy mix.

“Nuclear energy is safe, reliable, and an important source of electricity with zero carbon emission besides being economically competitive,” the PAEC said, adding that the NPPs were being operated under the safeguards of International Atomic Energy Agency.

Published in Dawn, March 5th, 2022

Opinion

Editorial

Ill omens
Updated 12 Feb, 2025

Ill omens

One wonders whether institutional leadership realises the long-term ramifications of the ongoing "remaking" of judiciary.
Sunken dreams
12 Feb, 2025

Sunken dreams

ANOTHER tragedy has struck Pakistani migrants seeking a better future. A boat capsizing off the Libyan coast has ...
Hate in India
12 Feb, 2025

Hate in India

HISTORY shows that rulers use hate speech to provoke hate crimes and ‘othering’ among communities. Indian Prime...
IMF scrutiny
Updated 11 Feb, 2025

IMF scrutiny

Strengthening foundations of the economic superstructure will help make the economy competitive and boost growth.
Shadow voices
11 Feb, 2025

Shadow voices

OVER the weekend, another ‘open letter’ addressed to the army chief and attributed to former prime minister ...
Paradise at a premium
11 Feb, 2025

Paradise at a premium

PAKISTAN’S recent triumph at the New York Travel and Adventure Show 2025, winning the Best Partner Pavilion Award,...