SNGPL wants connections quota to be raised to 1.2m

Published
0
SNGPL Managing Director Ali Javaid Hamdani said the over three million pending applications for new connections shows the massively increasing demand for gas in the country. — Reuters/File
SNGPL Managing Director Ali Javaid Hamdani said the over three million pending applications for new connections shows the massively increasing demand for gas in the country. — Reuters/File

LAHORE: The Sui Northern Gas Pipelines Limited (SNGPL) says that the only way the company can clear its backlog of millions of applications for new connections in Punjab and Khyber Pakhtunkhwa in the next three years is to increase its annual quota to 1.2 million domestic connections.

“The company has applied to the regulator — the Oil and Gas Regulatory Authority (Ogra) — to increase its quota to 1.2 million connections per annum, as the existing up to 500,000 connections is insufficient to clear the backlog of 3.2 million applications,” an official source in the petroleum division (ministry of energy) told Dawn. “To clear this huge backlog within three years or so, we need to be allowed to provide 1.2 million connections annually.”

Says backlog of 3.2m connection seekers can’t be cleared otherwise

In a recent meeting held in Islamabad, the source said, several schemes related to new gas connections in the constituencies of parliamentarians were discussed. The SNGPL representatives were asked to complete these schemes at the earliest, while they told the participants about the number of schemes, pending applications, urgent cases, available capacity, quota etc.

“The participants were told that the backlog is increasing fast with an addition of 800,000 applications a year that the company is unable to clear due to various reasons, including the allocated quota of up to half a million connections annually,” the official said.

He further said the meeting was told that Ogra had been requested to approve the company’s application seeking an increase in the quota to 1.2 million.

SNGPL Managing Director Ali Javaid Hamdani said the over three million pending applications for new connections shows the massively increasing demand for gas in the country. “Like water, gas has now become an essential commodity for everyone in Pakistan,” he added.

Calling gas “white gold” (like oil is generally called black gold in the Arab world), Mr Hamdani said along with clearing the huge backlog, the company will also have to enhance its capacity simultaneously.

Published in Dawn, July 30th, 2021

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Terrorist havens
07 Aug, 2026

Terrorist havens

DESPITE the use of both carrots and sticks by the international community, the Afghan Taliban refuse to cut their...
Mineral wealth
Updated 07 Aug, 2026

Mineral wealth

Any future agreements involving critical minerals must be subjected to rigorous legal, financial and technical scrutiny.
Growth denied
07 Aug, 2026

Growth denied

THE Sindh government’s agreement with the World Bank to combine health, nutrition, sanitation, social protection...
Need for dialogue
06 Aug, 2026

Need for dialogue

THE interior minister’s comments at an Islamabad seminar last week have sparked many a conversation about the ...
Bad press
06 Aug, 2026

Bad press

THE government’s move to impose restrictions on international media will not only alienate the foreign press, it...
Automobile concerns
06 Aug, 2026

Automobile concerns

PAKISTAN’S automobile industry is at a critical juncture. Sharp cuts in tariffs on the import of completely built...