ISLAMABAD: A slight change in PWD underpass design will delay the project by a month as it was supposed to be completed in June, but now it would be completed somewhere in July.

The sources said that due to change in design of a roundabout, the CDA extended the scope of the work.

However, official of engineering wing said that change in design of a roundabout was imperative which is not illegal as up to 15pc scope of the running project could be extended.

“In this case, there is around 10pc variation (change) in scope of work,” said a senior officer of CDA.

Last year, the CDA awarded the contract against Rs428 million - 19pc less than the estimated cost.

CDA officials said that one month delay did not matter and if the project was completed in July then too it was okay, but it should not be delayed any further.

An engineer of the CDA said the work was in full swing and efforts were being made to complete it in the given time. He confirmed that scope of the work has been increased.

Meanwhile, the work on expansion of Korang Bridge on expressway was also in progress, which according to CDA will be completed by December this year.

The expressway is one of busiest road and traffic jam is a routine on it particularly from Koral to G.T. Road. However, CDA officials believes that after completion of the two projects, the issue of traffic congestion will be resolved to some extent up to Korang Bridge.

They said that in next phase, the CDA will start widening of the road from Korang Bridge to G.T. Road.

The officials said that it was yet to be finalised who will carry out next phase, as federal government has also been making efforts to get the next phase done through public private partnership mode.

Earlier, the PML-N government in its last budget had earmarked Rs7 billion for expansion of expressway from Koral to G.T. Road, however, the PTI government later dropped the said project and decided to construct PWD underpass and expansion of Korang Bridge.

Now the government is planning to launch third and last phase through public-private partnership. “In both cases, either through public private partnership or through government funding, we have to execute the final phase of the expressway as this road is main interprovincial road,” said a CDA officer.

He said besides the two ongoing projects, the CDA is also planning to overhaul and widen the service road from Faizabad to Khanapul (towards Sohan side) of expressway.

Published in Dawn, April 22nd, 2021

Opinion

The Dar story continues

The Dar story continues

One wonders what the rationale was for the foreign minister — a highly demanding, full-time job — being assigned various other political responsibilities.

Editorial

Wheat protests
Updated 01 May, 2024

Wheat protests

The government should withdraw from the wheat trade gradually, replacing the existing market support mechanism with an effective new one over the next several years.
Polio drive
01 May, 2024

Polio drive

THE year’s fourth polio drive has kicked off across Pakistan, with the aim to immunise more than 24m children ...
Workers’ struggle
Updated 01 May, 2024

Workers’ struggle

Yet the struggle to secure a living wage — and decent working conditions — for the toiling masses must continue.
All this talk
Updated 30 Apr, 2024

All this talk

The other parties are equally legitimate stakeholders in the country’s political future, and it must give them due consideration.
Monetary policy
30 Apr, 2024

Monetary policy

ALIGNING its decision with the trend in developed economies, the State Bank has acted wisely by holding its key...
Meaningless appointment
30 Apr, 2024

Meaningless appointment

THE PML-N’s policy of ‘family first’ has once again triggered criticism. The party’s latest move in this...