Non-issuance of LoI delays first-ever LNG terminal at Port Qasim special zone

Published May 5, 2019
The PQA fails to issue the required letter of interest to the firm willing to invest $400m to set up the terminal. — AFP/File
The PQA fails to issue the required letter of interest to the firm willing to invest $400m to set up the terminal. — AFP/File

KARACHI: The Port Qasim Authority (PQA) has failed to issue the required letter of interest (LoI) to the Japanese firm willing to invest $400 million to set up a liquefied natural gas (LNG) terminal at a special LNG Zone under the guidelines of LNG Policy 2011.

According to Saad Ahmed Kazi of Tabeer Energy — the local representative of Mitsubishi — the firm has been working to secure a LoI to set up the first-ever LNG terminal at the dedicated LNG Zone equipped with separate navigation channel for the last six months but the approval is being delayed by the PQA.

He said that the firm has strictly followed the LNG Policy 2011 including PQA guidelines for the establishment of LNG project on a build-operate-and transfer basis and has also completed technical studies by incurring a cost of $10 million but the PQA has failed to award the LoI.

The 180-days delay is not only a contravention of the LNG Policy 2011, wherein it is stated that the PQA must convey its decision on proposal within 30 days, but is also immensely discouraging to foreign investors who are bringing in the much-needed Foreign Direct Investment (FDI) into the country.

Attempts were made to contact Acting Chairman PQA Asad Rafiq Chandna to get his version, but he did not reply to phone calls as well as SMS.

According to official documents available with Dawn, the investor has committed to set up navigational channel for the approach of exclusive LNG terminal (at Chann Wadoo) at its own cost and is also willing to install a multi-user pipeline and procure its own tugs. The Japanese investor has already obtained provisional no objection certificate (NOC) from PQA as well as provisional pipeline capacity approval from Ministry of Energy.

However, the PQA has also told the Japanese investor that the port is going to undertake ‘Technical Study’ to identify “LNG Zone” within port limits for establishment of all prospective LNG terminals.

But industry sources raised objections that since the LNG Zone had already been declared in 2011 as per the PQA board meeting then what was the reason for this delay. In fact, the documents disclose that in the same PQA meeting it was also decided that none other than the existing LNG terminal projects will be allowed to be constructed in the existing channel.

Above all the admiralty charts of the PQA till this day demarcate the LNG Zone to the area that constitutes a portion of the Chann Wadoo Creek and the Jhaari Creek.

As per preliminary plan, the LNG terminal at the specified zone would start functioning by end of next year provided due processing of the project was timely allowed. There are three other LNG projects in the pipeline to be set up at the main channel which is already congested.

The cost of setting up LNG terminal at main channel is at around $125-130m whereas the cost of the terminal proposed by the Japanese investor comes to around $400m because the operator is also going to lay down multi-user pipeline which is far away from the Sui Southern Gas Company tie-in-point (TIP).

Sources in the shipping industry have warned that PQA’s main channel is not feasible for additional LNG terminals because of severe traffic congestion. And in order to accommodate more LNG terminals; the government will have to spend around $300m for dredging 20m cubic meters.

Currently, two LNG terminals are operating in the PQA main channel and three are in the pipeline but even if these terminals are allowed to set-up at the site, at least two years would be required for dredging.

Published in Dawn, May 5th, 2019

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Weathering the storm
Updated 29 Apr, 2024

Weathering the storm

Let 2024 be the year when we all proactively ensure that our communities are safeguarded and that the future is secure against the inevitable next storm.
Afghan repatriation
29 Apr, 2024

Afghan repatriation

COMPARED to the roughshod manner in which the caretaker set-up dealt with the issue, the elected government seems a...
Trying harder
29 Apr, 2024

Trying harder

IT is a relief that Pakistan managed to salvage some pride. Pakistan had taken the lead, then fell behind before...
Return to the helm
Updated 28 Apr, 2024

Return to the helm

With Nawaz Sharif as PML-N president, will we see more grievances being aired?
Unvaxxed & vulnerable
Updated 28 Apr, 2024

Unvaxxed & vulnerable

Even deadly mosquito-borne illnesses like dengue and malaria have vaccines, but they are virtually unheard of in Pakistan.
Gaza’s hell
Updated 28 Apr, 2024

Gaza’s hell

Perhaps Western ‘statesmen’ may moderate their policies if a significant percentage of voters punish them at the ballot box.