Neelum-Jhelum project closed for month-long inspection

Published January 6, 2019
The unit would remain closed for 29 days until Feb 2. — File
The unit would remain closed for 29 days until Feb 2. — File

LAHORE: The power house of 969MW Neelum-Jhelum Hydropower Project (NJHP) was shut down on Saturday due to inspection.

The unit would remain closed for 29 days until Feb 2 because of inspection, and is expected to resume power generating operations from Feb 3 onwards, according to official sources.

“The project is now due for a thorough inspection of the electro-mechanical equipments from Jan 5 to Feb 2. The low water flow season has been chosen for carrying out the inspection,” stated the Water and Power Development Authority’s (Wapda) press release.

“The project is bracing up for full generation during the next high flow season that will start from April onwards. It has been in operation for almost eight months since its commissioning.”

Neelum-Jhelum Hydropower Project went into operation with commissioning of its first unit on Apr 13, 2018. All four units went were operatlionalised in phases by Aug 14, 2018.

Since its commissioning, the NJHP has injected over 1.8 billion units (kWh) to the national grid.

The spokesman said the low flow period of Neelum River lasts from September to March, after which it provides the required 280 cubic metre per second of water to run all its four units.

The least flow in the river is during January which is why the month has been chosen for inspection of the draft tubes, flap gates, 3.5km underground tailrace, surge shaft, generating units and auxiliary equipment entailing dewatering of tailrace.

Published in Dawn, January 6th, 2019

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Missing links
Updated 27 Apr, 2024

Missing links

As the past decades have shown, the country has not been made more secure by ‘disappearing’ people suspected of wrongdoing.
Freedom to report?
27 Apr, 2024

Freedom to report?

AN accountability court has barred former prime minister Imran Khan and his wife from criticising the establishment...
After Bismah
27 Apr, 2024

After Bismah

BISMAH Maroof’s contribution to Pakistan cricket extends beyond the field. The 32-year old, Pakistan’s...
Business concerns
Updated 26 Apr, 2024

Business concerns

There is no doubt that these issues are impeding a positive business clime, which is required to boost private investment and economic growth.
Musical chairs
26 Apr, 2024

Musical chairs

THE petitioners are quite helpless. Yet again, they are being expected to wait while the bench supposed to hear...
Global arms race
26 Apr, 2024

Global arms race

THE figure is staggering. According to the annual report of Sweden-based think tank Stockholm International Peace...