LAHORE: The fourth and last unit of the Neelum-Jhelum Hydropower Project (NJHP) was synchronised with national grid on Monday after it started generating over 200 megawatts on a trial basis.

During the project’s trial run, the unit will be tested on various loads ranging up to 242MW.

“With successful commissioning of its all four units, the NJHP is expected to attain its installed generation capacity of 969MW in a couple of days,” said a spokesperson for the Water and Power Development Authority.

Three units at the project have already been generating 726MW of electricity on trial basis; thus far, they have contributed around 900 million electricity units to the national grid.

It may be recalled that commercial operation of fourth unit at NJHP was delayed in May after experts identified some technical issues in the machine during various tests and sought replacement for some parts.

This unit had actually started trial generation in April and later went through various tests required for commercial operation. The unit injected more than 1.3m units of electricity during test run.

However, while testing the unit, the ‘run-outs’ exceeded specifications. Therefore, project consultants concluded that in order to smoothly operate the unit for its designated life, its parts — ‘labyrinth’ and ‘lower sleeve’ — should be replaced with new ones.

Published in Dawn, August 14th, 2018

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...
Punishing evaders
02 May, 2024

Punishing evaders

THE FBR’s decision to block mobile phone connections of more than half a million individuals who did not file...
Engaging Riyadh
Updated 02 May, 2024

Engaging Riyadh

It must be stressed that to pull in maximum foreign investment, a climate of domestic political stability is crucial.
Freedom to question
02 May, 2024

Freedom to question

WITH frequently suspended freedoms, increasing violence and few to speak out for the oppressed, it is unlikely that...