ISLAMABAD: One of the new RLNG power plants the government is relying on has successfully completed its critical reliability test run, according to a press release. The plant is located in Haveli Bahadur Shah of Jhang district.

The project is expected to add up to 1,230 megawatts (MW) to the national grid — enough to meet the needs of 2.5 million households.

SEPCOIII, a wholly-owned subsidiary of Power Construction Corporation of China, is the engineering, procurement and construction contractor for the project.

Power company clarifies

Meanwhile, the National Power Parks Management Company (NPPMC), a government-owned organisation which is building the three RLNG power plants, has clarified a report carried by Dawn in its March 26 issue under the headline, “Cabinet worried over delay in 6,000MW power plants”. No request for open cycle operation after conversion period has been submitted by NPPMCL to Nepra, the company said.

The NPPMC further said the date for commencement of commercial operations for Haveli Bahadur Shah is April this year while that for Balloki is May.

The technology being used in the plants is new, but it has been tested in several countries before its installation in Pakistan. Prominent among them are the United States, Japan, France and Russia.

Published in Dawn, March 28th, 2018

Opinion

Editorial

Ties with Tehran
Updated 24 Apr, 2024

Ties with Tehran

Tomorrow, if ties between Washington and Beijing nosedive, and the US asks Pakistan to reconsider CPEC, will we comply?
Working together
24 Apr, 2024

Working together

PAKISTAN’S democracy seems adrift, and no one understands this better than our politicians. The system has gone...
Farmers’ anxiety
24 Apr, 2024

Farmers’ anxiety

WHEAT prices in Punjab have plummeted far below the minimum support price owing to a bumper harvest, reckless...
By-election trends
Updated 23 Apr, 2024

By-election trends

Unless the culture of violence and rigging is rooted out, the credibility of the electoral process in Pakistan will continue to remain under a cloud.
Privatising PIA
23 Apr, 2024

Privatising PIA

FINANCE Minister Muhammad Aurangzeb’s reaffirmation that the process of disinvestment of the loss-making national...
Suffering in captivity
23 Apr, 2024

Suffering in captivity

YET another animal — a lioness — is critically ill at the Karachi Zoo. The feline, emaciated and barely able to...