ISLAMABAD: The Rs30 billion worth of much-delayed Golen Gol Hydropower Project in Chitral District of Khyber Pakhtunkhwa is getting ready for power generation in about two months, however locals may not be able to consume the electricity owing to distribution constraints.

Informed sources in the Power Division told Dawn on Tuesday that the first 36-megawatt unit of the project was nearing completion and expected to start generation before Dec 31 under a revised deadline set by former prime minister Nawaz Sharif.

During a visit to Chitral early last year, Mr Sharif had announced dedication of first unit (36MW) to the marble city and people of Chitral and adjoining areas who complained excessive loadshedding, low-voltage and fewer electricity connections.

He had directed Wapda to accelerate project construction and ordered the Peshawar Electric Supply Company (Pesco) to augment distribution system to absorb 36MW electricity from the new unit to meet requirements of the area people.

The sources said while Wapda mobilised additional resources to deliver on the government directive, Pesco struggled on its part to lay lines for supplying additional electricity from Golen Gol to Chitral and adjoining areas at around 22-kilometre distance. Even if Wapda is able to operationalise first unit, “the laxity on part of Pesco can cost dearly to the people in Chitral,” an official said.

“The only action taken by Pesco so far is the submission of a PC-I amounting to Rs5bn to the federal government but was not actively pursuing for its approval by the Planning Commission. When contacted, a Wapda spokesperson said the authority was on schedule to deliver the first unit by December, but declined to comment on the readiness of the distribution company to evacuate power.

The 108MW project was originally planned to start in 1996 but actually commenced construction in 2002 with a completion deadline of 2011. Its approved cost was estimated at Rs7bn in 2002 but was revised to Rs29.1bn in September 2016. As of last month, the project is reported to have achieved 81pc physical progress.

A consortium of international lenders was also funding the project.

Published in Dawn, September 27th, 2017

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Enter the deputy PM

Enter the deputy PM

Clearly, something has changed since for this step to have been taken and there are shifts in the balance of power within.

Editorial

All this talk
Updated 30 Apr, 2024

All this talk

The other parties are equally legitimate stakeholders in the country’s political future, and it must give them due consideration.
Monetary policy
30 Apr, 2024

Monetary policy

ALIGNING its decision with the trend in developed economies, the State Bank has acted wisely by holding its key...
Meaningless appointment
30 Apr, 2024

Meaningless appointment

THE PML-N’s policy of ‘family first’ has once again triggered criticism. The party’s latest move in this...
Weathering the storm
Updated 29 Apr, 2024

Weathering the storm

Let 2024 be the year when we all proactively ensure that our communities are safeguarded and that the future is secure against the inevitable next storm.
Afghan repatriation
29 Apr, 2024

Afghan repatriation

COMPARED to the roughshod manner in which the caretaker set-up dealt with the issue, the elected government seems a...
Trying harder
29 Apr, 2024

Trying harder

IT is a relief that Pakistan managed to salvage some pride. Pakistan had taken the lead, then fell behind before...