ISLAMABAD: The Rs30 billion worth of much-delayed Golen Gol Hydropower Project in Chitral District of Khyber Pakhtunkhwa is getting ready for power generation in about two months, however locals may not be able to consume the electricity owing to distribution constraints.

Informed sources in the Power Division told Dawn on Tuesday that the first 36-megawatt unit of the project was nearing completion and expected to start generation before Dec 31 under a revised deadline set by former prime minister Nawaz Sharif.

During a visit to Chitral early last year, Mr Sharif had announced dedication of first unit (36MW) to the marble city and people of Chitral and adjoining areas who complained excessive loadshedding, low-voltage and fewer electricity connections.

He had directed Wapda to accelerate project construction and ordered the Peshawar Electric Supply Company (Pesco) to augment distribution system to absorb 36MW electricity from the new unit to meet requirements of the area people.

The sources said while Wapda mobilised additional resources to deliver on the government directive, Pesco struggled on its part to lay lines for supplying additional electricity from Golen Gol to Chitral and adjoining areas at around 22-kilometre distance. Even if Wapda is able to operationalise first unit, “the laxity on part of Pesco can cost dearly to the people in Chitral,” an official said.

“The only action taken by Pesco so far is the submission of a PC-I amounting to Rs5bn to the federal government but was not actively pursuing for its approval by the Planning Commission. When contacted, a Wapda spokesperson said the authority was on schedule to deliver the first unit by December, but declined to comment on the readiness of the distribution company to evacuate power.

The 108MW project was originally planned to start in 1996 but actually commenced construction in 2002 with a completion deadline of 2011. Its approved cost was estimated at Rs7bn in 2002 but was revised to Rs29.1bn in September 2016. As of last month, the project is reported to have achieved 81pc physical progress.

A consortium of international lenders was also funding the project.

Published in Dawn, September 27th, 2017

Opinion

Editorial

Khorasani’s killing
11 Aug, 2022

Khorasani’s killing

OMAR Khalid Khorasani, a dreaded TTP ‘commander’, lived by the sword and very much died by the sword. But beyond...
Gross overreaction
Updated 11 Aug, 2022

Gross overreaction

The government has already done considerable damage to itself with its indelicate handling of the situation.
Dadu deaths
11 Aug, 2022

Dadu deaths

DISEASES that are usually mild and preventable in countries with developed healthcare systems often prove to be...
Beyond the pale
Updated 09 Aug, 2022

Beyond the pale

When such ugliness is unleashed, everyone at some point suffers the fallout.
Burying Gaza
Updated 10 Aug, 2022

Burying Gaza

One fails to understand how the senseless killing of a child can be brushed so coldly under the carpet.
Celebrate the athlete
09 Aug, 2022

Celebrate the athlete

TALK about delivering on your promise: javelin thrower Arshad Nadeem did that in the grandest style at the...