LAHORE: The Federal Government Inspector of Railways (FGIR) had time and again expressed reservations about the ‘inadequate’ computer-based Interlocking Signalling System installed on Lodhran and Shahdara sections, where Awam Express smashed into a goods train on Sept 15.

The FGIR had warned the Pakistan Railways (PR) authorities not to make operational the new signalling system without installing automatic train protection gadgets in the locomotives hauling passenger trains on the route, an officer of the Ministry of Railways told Dawn On Sunday.

“The FGIR is the safety controlling authority in the PR. No train can be operated on a route if after inspection the FGIR finds that the railway (track, allied facilities and rolling stock) do not fulfill requirements essential for the public carriage of passengers,” said the officer while quoting from the Railways Act 1890.

Section 18 of the Act reads: “A railway shall not be opened for the public carriage of passengers until the federal government or an inspector empowered by the central government in this behalf, has by order sanctioned the opening thereof for that purpose.”

Section 19 (2) reads: “If in the opinion of the inspector the railway cannot be so open without danger to the public, if he shall state that opinion, together with the grounds therefore, to the central government and the federal government may thereupon order the railway administration to postpone the opening of the railway.”

The PR had in February 2010 entered into an agreement with a consortium of German firm Bombardier Transportation and China Railway Signal and Communication in order to make rail journey safer and faster on its Lodhran-Shahdara section.

Under the agreement, latest computer-based interlocking signal and auto-block systems were to be installed on some 31 stations in addition to installation of automatic train protection system in locomotives dedicated to operate trains on the Lodhran-Shahdara sections.

“Work on the project was to begin on May 10, 2010, and completed by May 9, 2013, at the estimated cost of Rs10.720 billion according to the PC-1,” said the officer while seeking anonymity.

Since the consortium could not even start work on the project within the stipulated time-frame, the deadline was extended to June 30, 2016.

Again, inordinate delay in completion of the project not only necessitated revision in its cost to Rs17.4 billion but also the deadline to May 10, 2017.

In the meanwhile, the PR paid Rs12.5 billion to the consortium, including 100 per cent advance payment of Rs1.5 billion on account of Automatic Train Protection System.

So far, the consortium has installed and made operational computer-based interlocking signal and auto-block system on seven railway stations between Lodhran and Riazabad. However, the Automatic Train Protection System has yet to be installed in locomotives for non-provision of equipment and software by the consortium.

“Can installation of the system on 24 stations be completed in less than a year (of the deadline) when the consortium took six years to upgrade seven stations?” said the officer.

Published in Dawn, September 26th, 2016

Opinion

Editorial

Judiciary’s SOS
Updated 28 Mar, 2024

Judiciary’s SOS

The ball is now in CJP Isa’s court, and he will feel pressure to take action.
Data protection
28 Mar, 2024

Data protection

WHAT do we want? Data protection laws. When do we want them? Immediately. Without delay, if we are to prevent ...
Selling humans
28 Mar, 2024

Selling humans

HUMAN traders feed off economic distress; they peddle promises of a better life to the impoverished who, mired in...
New terror wave
Updated 27 Mar, 2024

New terror wave

The time has come for decisive government action against militancy.
Development costs
27 Mar, 2024

Development costs

A HEFTY escalation of 30pc in the cost of ongoing federal development schemes is one of the many decisions where the...
Aitchison controversy
Updated 27 Mar, 2024

Aitchison controversy

It is hoped that higher authorities realise that politics and nepotism have no place in schools.