KARACHI, July 9: The Karachi Electric Supply Company (KESC) has put into effect its rain emergency plan with a view to improving its capability to quickly restoring services that may disrupt during rains.

In a statement issued here the KESC said that it wanted to manage increased workload as a consequence of rains through effective coordination and timely positioning of manpower and material stock.

The power utility advised the general public to keep away from rain-created hazards, including snapped wires, wet electric installations inside and outside buildings and inform the KESC about any emergency. The plan envisaging closer inter-departmental coordination and pre-practiced drills to ensure seamless operations in times of emergency would act as a guideline for all rain emergency actions, it said.

According to the plan, the KESC would alert field staff after receiving weather reports of approaching rains and notify emergency need to rectify pending faults on information received from central and regional nerve centres, especially set up for the purpose, the statement added.

These centres would collect all information during rain emergency from all public complaint offices and support departments maintaining low-tension and high-tension transmission lines and distribution network.

“Field maintenance teams equipped with required machines, special tools and lighting arrangements, etc, will work in three shifts round the clock to ensure rapid rectification of faults.

“The KESC top management will directly be monitoring situation through fault reports at an eight hour frequency initiated by all area offices. At times of emergency, these reports will be initiated every four hours.

“All maintenance and support vehicles have been made available for prompt deployment at location of fault while standby vehicles will also be ready to move immediately in case of a vehicle breaking down.

“Like previous years, safety of field staff will be observed as highest priority. In cases of rectifying faults, line isolation shall be ensured before undertaking work,” the statement added.

All regional coordinators would remain in contact with respective town administrators’ offices to mobilise KESC resources as per greatest need of public.—PPI

Opinion

Editorial

IMF’s projections
Updated 18 Apr, 2024

IMF’s projections

The problems are well-known and the country is aware of what is needed to stabilise the economy; the challenge is follow-through and implementation.
Hepatitis crisis
18 Apr, 2024

Hepatitis crisis

THE sheer scale of the crisis is staggering. A new WHO report flags Pakistan as the country with the highest number...
Never-ending suffering
18 Apr, 2024

Never-ending suffering

OVER the weekend, the world witnessed an intense spectacle when Iran launched its drone-and-missile barrage against...
Saudi FM’s visit
Updated 17 Apr, 2024

Saudi FM’s visit

The government of Shehbaz Sharif will have to manage a delicate balancing act with Pakistan’s traditional Saudi allies and its Iranian neighbours.
Dharna inquiry
17 Apr, 2024

Dharna inquiry

THE Supreme Court-sanctioned inquiry into the infamous Faizabad dharna of 2017 has turned out to be a damp squib. A...
Future energy
17 Apr, 2024

Future energy

PRIME MINISTER Shehbaz Sharif’s recent directive to the energy sector to curtail Pakistan’s staggering $27bn oil...