ISLAMABAD, July 28: The Auxiliary Spillway Project at Simly Dam, which aims at increasing storage capacity and avoiding water wastage, will be completed by the end of the current year with an estimated cost of Rs300 million, a senior CDA official told Dawn on Sunday.

“Some 70 per cent work on the project has already been completed,” he said, adding that under-construction rear wall of the auxiliary spillway would be completed by the next month.

With the completion of the project, the maximum water level at the dam will be increased to 2,315 feet against the current highest level of 2,295 feet, he added.

“The authority will be able to save 1.8 million gallon per day (MGD) of water after the completion of the project,” he added.

A source said the CDA had started the project some five years ago, but due to financial constraints, it could not be completed.

He said the Wapda officials, who had prepared a survey report on Simly Dam some years ago, suggested the CDA to construct the auxiliary spillway, which would be used for releasing a required quantity of water from the reservoir.

He said an intech-siphon — a pump — would be installed at the filtration plant of the dam to supply treated water to the residents of the federal capital, in case of non-functioning of the filtration plant.

The CDA has also conducted a study for the construction of a check dam at Simly Dam’s tributary, the source said.

Another authority official said more than the required quantity of water spilled out of the dam, when the existing spillway was opened. This wastage can be avoided after the construction of the auxiliary spillway, he said.

Another official told Dawn that depending upon the loss of water due to evaporation and seepage in the dam, the water supply was reduced or increased by the CDA.

Responding to a query, he said the dead level of the Simly Dams was higher, compared to that of other dams because its water was mainly used for drinking and domestic purposes.

Opinion

Editorial

Sustainable path?
Updated 13 Jun, 2026

Sustainable path?

The FY27 budget is the first clear signal that the government is ready to transition from stabilisation to growth.
Prioritising education
13 Jun, 2026

Prioritising education

THOUGH the improvement in the country’s literacy rate may be slight, as highlighted by the Economic Survey, it ...
Poverty’s rise
13 Jun, 2026

Poverty’s rise

AS attention turns to the government’s plans for the coming fiscal year, one set of figures deserves particular...
A difficult story
Updated 12 Jun, 2026

A difficult story

Unless productivity becomes the dominant target of economic policy, Pakistan will continue to oscillate between crises and fragile recovery.
Rough waters
12 Jun, 2026

Rough waters

AMONGST the key potential triggers for fresh conflict in South Asia is water. The Indian state is behaving in an...
Politicised football
12 Jun, 2026

Politicised football

ALMOST three-and-half years since Lionel Messi led Argentina to FIFA World Cup glory, the latest edition of...