KARACHI, May 28: The repair work of KWSB’s 84-inch dia pipeline, Siphon-19, was completed on Monday night and water supply to affected parts of the city resumed from Tuesday morning.

It may be mentioned here that Siphon-19, which supplies water from the Indus source to COD, had developed a major leak near Karachi University.

The KWSB started repair work on Sunday night and work was to be completed in 48 hours as per schedule. But on the directive of the KWSB MD, Brig Behram Khan, the line was repaired in 18 hours and water released into the siphon on Monday night.

At present, the KWSB said, 470 mgd water is being supplied to the city from all sources and all areas are being provided supplies as per quota.

A KWSB spokesman said that the water supply position in North Nazimabad, Nazimabad and Buffer Zone is normal and these areas are being provided water from the Sakhi Hasan Pumping Station through four pumping motors.—APP

Opinion

Editorial

Sustainable path?
Updated 13 Jun, 2026

Sustainable path?

The FY27 budget is the first clear signal that the government is ready to transition from stabilisation to growth.
Prioritising education
13 Jun, 2026

Prioritising education

THOUGH the improvement in the country’s literacy rate may be slight, as highlighted by the Economic Survey, it ...
Poverty’s rise
13 Jun, 2026

Poverty’s rise

AS attention turns to the government’s plans for the coming fiscal year, one set of figures deserves particular...
A difficult story
Updated 12 Jun, 2026

A difficult story

Unless productivity becomes the dominant target of economic policy, Pakistan will continue to oscillate between crises and fragile recovery.
Rough waters
12 Jun, 2026

Rough waters

AMONGST the key potential triggers for fresh conflict in South Asia is water. The Indian state is behaving in an...
Politicised football
12 Jun, 2026

Politicised football

ALMOST three-and-half years since Lionel Messi led Argentina to FIFA World Cup glory, the latest edition of...