KARACHI, Sept 4: Massive tripping of the Karachi Electric Supply Company’s extra high tension (EHT) circuits knocked out many grid stations resulting in the suspension of power supply to a large number of city areas at different times on Thursday.

Tripping of the KESC’s Valika –Gul Ahmad 220 KV EHT circuit had a cascading impact on at least nine grid stations primarily serving the industrial area and localities around it, said sources.

Early in the day tripping was registered in Gulshan-Landhi EHT circuit which denied power supply to a vast area for several hours, including Gulshan-i-Iqbal, Gulistan-i-Jauhar, Malir, Landhi etc and various adjoining areas

Around 1pm tripping occurred in Valika –Gul Ahmad circuit which affected Baldia, Lyari, Orangi, Old Town, West Wharf, Valika, Site, Mauripur and Haroonabad grid stations. On account of the tripping North Nazimabad and adjoining areas were also affected.

The cause of the tripping is yet to be ascertained but it certainly created a massive gap in power supply by the utility on a day when all its units of Bin Qasim Power plant were operating and producing around 845 megawatts. Nevertheless two units of the plant, 3 and 4 were producing 70MW and 80MW respectively.

Outages were also experienced in Federal B Area and North Karachi industrial areas until mid day reportedly due to tripping of lines around six times. Interestingly, when complaints were lodged with the relevant authorities, the consumers were told that only one tripping had occurred.

Meanwhile, the KESC faced a maximum shortfall of 280 megawatts in meeting around 2,200MW overall demand of power supply to the city.

Around 6:30pm the shortfall of electricity was around 215 megawatts with the Defence Cogen desalination plant giving 77MW electricity. It is worth mentioning that the Karachi Nuclear Power Plant resumed power supply to the KESC at about 8.30pm after remaining dormant since Aug 22.

The KESC officials said that like Sept 3 efforts would be made once again to spare dwellers of the city of power load-shedding 15 minutes prior to the Iftar time.

A spokesman for the power utility has said that the KESC has been doing its best to avoid the instances of power load-shedding during Sehar and Iftar times. Any breakdown or fault occurred at these times would be addressed immediately, he said.

Opinion

Editorial

Sustainable path?
13 Jun, 2026

Sustainable path?

THE FY27 budget is the first clear signal that the government is ready to transition from stabilisation to growth ...
Prioritising education
13 Jun, 2026

Prioritising education

THOUGH the improvement in the country’s literacy rate may be slight, as highlighted by the Economic Survey, it ...
Poverty’s rise
13 Jun, 2026

Poverty’s rise

AS attention turns to the government’s plans for the coming fiscal year, one set of figures deserves particular...
A difficult story
Updated 12 Jun, 2026

A difficult story

Unless productivity becomes the dominant target of economic policy, Pakistan will continue to oscillate between crises and fragile recovery.
Rough waters
12 Jun, 2026

Rough waters

AMONGST the key potential triggers for fresh conflict in South Asia is water. The Indian state is behaving in an...
Politicised football
12 Jun, 2026

Politicised football

ALMOST three-and-half years since Lionel Messi led Argentina to FIFA World Cup glory, the latest edition of...