ISLAMABAD, Nov 14: The much talked about multi-billion Clean Drinking Water for All (CDWA) project seems heading nowhere after its shifting from the environment ministry to the ministry of industries and efforts are being made to get it back, Dawn has learnt.

Noticing the slow pace of work on the project, the prime minister a couple of months ago had directed the ministry of industries to take over the implementation of the project. However, sources told Dawn that the environment ministry was still vying to get the project back.

The project came to standstill with the change of portfolios in the federal cabinet on April 25 this year. The then federal minister for environment Maj (retd) Tahir Iqbal and minister for Kashmir affairs Faisal Saleh Hayat swapped their portfolios.

According to the PC-I of the project, the provinces through local governments were to set up water filter plants at union council level, but the new minister wanted more control over the project which had resulted in its delay, the sources said.

Subsequently, during a presentation made to President Gen Pervez Musharraf, he expressed disappointment over the execution of the project and asked the prime minister to speed up the work.

Prime Minister Shaukat Aziz directed the ministry of industries and special initiatives to take over the project.

When contacted, CDWA Project Director Brig Sikander Javed said the project was still in the process of switching over to the industries ministry and would soon be made operational again.

But sources at the environment ministry said that the environment minister had requested the prime minister to return the project to his ministry.

The CEDW envisages installation of around 6,035 water purification plants of different capacities (500/1,000/2,000 gallons per hour), one in each union council of the country according to the needs of its population. The project has been included in the Mid-Term Development Framework 2,005-10 with an allocation of over Rs7 billion.

With the recent developments, the government is unlikely to meet the target of completing the project by December 2,007, the sources said.

Opinion

Editorial

A difficult story
12 Jun, 2026

A difficult story

WHILE launching the Economic Survey 2026, Finance Minister Muhammad Aurangzeb told a hopeful story of economic...
Politicised football
12 Jun, 2026

Politicised football

ALMOST three-and-half years since Lionel Messi led Argentina to FIFA World Cup glory, the latest edition of...
Rough waters
12 Jun, 2026

Rough waters

AMONGST the key potential triggers for fresh conflict in South Asia is water. The Indian state is behaving in an...
GB polls’ aftermath
Updated 11 Jun, 2026

GB polls’ aftermath

The new administration must address the region’s issues proactively.
Peace in retreat
11 Jun, 2026

Peace in retreat

THE ceasefire announced in April was supposed to create space for negotiations. Instead, it has been repeatedly...
A few good men
11 Jun, 2026

A few good men

IT was a brave move, no doubt. This Tuesday, in the land of the Afghan Taliban, a few good men decided to take a...