Battery boom & grid-cost dilemma

Published Updated
0

Pakistan’s battery boom is reshaping the electricity market. Without smarter tariffs and market rules, the cost of maintaining the grid could increasingly fall on consumers who cannot afford to leave it. The country imported an estimated 6.004 gigawatt-hours (GWh) of lithium-ion batteries between January 2024 and June 2026, according to a consultant’s analysis of customs data prepared for the Power Division. Separately, the Power Division has announced plans to tender four battery-storage pilot projects of 10 megawatt-hours (MWh) each across Lesco, Mepco, Iesco and Pesco. These figures are not directly comparable: one represents cumulative imports across market segments, the other a proposed public pilot. But the contrast is striking. Private investment in storage is moving much faster than the state’s initial grid-level response.

Solar has already transformed the daytime electricity market. Renewables first estimated that distributed solar generated around 51 terawatt-hours (TWh) in FY-25, equivalent to 46pc of the 111 TWh of grid-supplied electricity. This is a modelled estimate, not an officially metered national total, but it illustrates the scale of the shift. Batteries are now extending that change into the evening. A solar household without storage still relies on the grid after sunset; one with a battery can substantially reduce that dependence. The grid risks becoming a back-up supplier for customers who once depended on it throughout the day.

Policy has sharpened the incentive. Nepra’s Prosumer Regulations, notified in February 2026, introduced net billing for new arrangements: electricity supplied by the distribution company is charged at the applicable tariff, while exported electricity is credited at the national average energy purchase price. This makes self-consumption more attractive than exporting surplus solar generation. Net billing may have contributed to battery adoption, although high tariffs, reliability concerns and regional energy disruptions have also played a role. The timing is suggestive, not proof of causation.

Battery adoption exposes fault lines in power tariff

Who pays as customers reduce their grid purchases? Battery owners bear the capital, financing, degradation and replacement costs. But the fixed costs of generation contracts, transmission and distribution do not disappear when households buy fewer units from the grid. Unless tariffs adapt, more of these costs may fall on consumers who remain dependent on grid electricity. Capacity payments alone reached Rs1.71 trillion in FY-26. The concern is not that battery owners pay nothing; it is that unavoidable system costs may be distributed increasingly unequally.

The affordability divide is already visible. At a parliamentary forum, the Pakistan Solar Association’s vice-chairperson estimated that taxes and customs duties add 35-40pc to storage costs, while a basic 5 kWh battery costs upwards of Rs250,000. These are industry estimates, not official market averages, but they illustrate the barrier facing lower-income households. Storage is a private investment for those who can afford it, while the costs of maintaining the central grid remain a shared responsibility.

The state’s response remains unsettled. The published Indicative Generation Capacity Expansion Plan (IGCEP) identifies a system-level storage requirement of 750 MWh for FY-26, rising to 1,500 MWh by FY-31. These are planning estimates, not an immediate procurement commitment.

Meanwhile, Nepra declined in September to approve a separate proposed $900 million battery investment, citing the need for stronger technical and economic justification. The government is, therefore, announcing small pilots, identifying longer-term storage needs and reconsidering large-scale investment at the same time. Pakistan needs a coherent approach rather than disconnected initiatives. Four steps are essential.

First, price evening flexibility carefully. A Power Division adviser has proposed enhanced evening discharge rates of Rs18–22 per unit between 5pm and 10pm. The proposal should be tested against verified avoided costs: marginal fuel, balancing services and demonstrable network benefits. Charging energy, conversion losses, degradation and metering costs must also be deducted. A household battery does not automatically reduce capacity payments owed under existing power-purchase agreements. Capacity value should count only where reliable storage demonstrably defers future capacity procurement or investment. Pay for net system value, not simply for electricity discharged.

Second, extract flexibility from assets already on the bill. Before financing additional evening capacity, Pakistan should assess what its existing generation fleet can deliver. CPEC-financed coal plants deserve particular attention because they represent substantial contracted investments. However, their ability to ramp up output must be tested plant by plant, considering minimum stable generation, ramp rates, start-up time, heat-rate penalties and contractual restrictions.

A World Bank study found that contractual ramp-rate provisions for Pakistani thermal plants were often more restrictive than their technical potential. Where feasible, revised operating arrangements or separate agreements could reward additional, verified services without paying twice for existing obligations.

Third, exchange targeted tax relief for safety and visibility. Pakistan is not starting from a regulatory vacuum. Nepra’s Prosumer Regulations provide interconnection arrangements for distributed-generation systems incorporating storage and require grid-connected inverters to meet UL 1741 standards (primary safety and performance standards for solar-related equipment). However, a comprehensive framework covering battery safety, registration, testing, recycling and grid participation across household, commercial and utility-scale applications remains necessary. Reduced duties should be linked to recognised certification, utility registration and interconnection compliance. Registration alone does not make a battery dispatchable; resources offering grid services must also meet appropriate monitoring and performance requirements.

Fourth, procure utility storage where it can defer network costs.

A Power Division adviser has indicated that Nepra is moving towards recognising battery storage as a regulated asset for distribution companies. This could help relieve overloaded transformers and grid stations, but the designation should be accompanied by clear rules. Each project should pass a location-specific assessment showing that its lifetime cost is lower than the conventional network investment or operating expenditure it can demonstrably defer, while accounting for reliability benefits. Storage should not become another asset whose costs are passed on to consumers without measurable returns.

Pakistan should not try to reverse the solar move. It must make distributed investment work alongside the central grid rather than allowing the two to evolve in conflict. Those who provide verified flexibility should be compensated fairly, but consumers without storage should not become the default financiers of an unmanaged transition. A grid becomes fragile not simply when customers leave, but when the cost of keeping it reliable is left to those with the fewest alternatives. Pakistan should decide who pays for flexibility before the market decides for it. n

The writer specialises in energy policy

Published in Dawn, The Business and Finance Weekly, November 16th, 2026

Opinion

Editorial

LG malaise
16 Nov, 2026

LG malaise

THE repeated delays in local government elections in Islamabad expose the reluctance of the government to strengthen...
Smog diplomacy
16 Nov, 2026

Smog diplomacy

EACH winter, Lahore and Delhi engage in a peculiar rivalry, trading places at the top of the world’s air-pollution...
Wild trophies
16 Nov, 2026

Wild trophies

THE elite fixation on housing wild beasts as status symbols is an invitation to tragedy. A farmhouse owner and a...
Muddled hierarchy
Updated 15 Nov, 2026

Muddled hierarchy

The jurisdiction of the two courts and a mechanism for settling disputes between them should be spelt out in law, not left to judges to fight over.
Growing crisis
Updated 15 Nov, 2026

Growing crisis

Calling population growth a national emergency is easy. Ensuring that the response reaches the people who need it is the real challenge.
Organised rackets
15 Nov, 2026

Organised rackets

ON the International Day against Transnational Organised Crime, observed today, Pakistan finds itself in a tight...