LOWER DIR: Amid conflicting claims about the operational status of the Koto hydropower station, a delegation of Dir Think Tank (DTT), a civic body of intellectuals, visited the unit the other day to assess ground realities following reports that power generation had been suspended.

The delegation, led by Ajmal Khan Advocate and Prof Wali Rehman, included social activists Akbar Khan, Ibrash Pasha, former Wapda executive engineer Javed and mediapersons. The visit was aimed at identifying reasons behind delays in making the power station fully operational.

The delegation first inspected the intake site and later examined repair work at the channel box.

Mushtaq Hussain, supervisor of the construction company, informed the team that the project had not yet been formally handed over to the Pakhtunkhwa Energy Development Organisation (Pedo).

Under contractual terms, the contractor will remain responsible for addressing any technical faults or repair work for one year.

He pointed out that water seepage in the channel box had caused subsidence at several locations.

Pedo assistant director Mohsin Khan explained that May, June, July and August were high flow months and the unit would generate maximum electricity during this period.

Talking about the delay in its completion, he said the original design would have required demolition of several houses, but following resistance from the local community, the design was altered, shifting the channel from hard rock to filled and agricultural land with softer soil. He said the issue could have been mitigated through soil testing, but the channel subsided within months.

Engineers accompanying the delegation said such issues were not uncommon in hydropower projects, citing the Ghazi Barotha project as an example.

Published in Dawn, January 15th, 2026

Opinion

Editorial

Narrative confusion
Updated 14 Oct, 2026

Narrative confusion

The centre must say clearly how long it intends it to last, what it hopes to achieve in that time, and how the province’s elected mandate will be restored.
El Niño’s long reach
14 Oct, 2026

El Niño’s long reach

THE extraordinary El Niño gathering strength in the Pacific could make 2026 the hottest year on record, with 2027...
Deeper poverty
14 Oct, 2026

Deeper poverty

PAKISTAN’S poverty crisis is far deeper than official indicators suggest. While the government celebrates economic...
Yemen escalation
Updated 13 Oct, 2026

Yemen escalation

Such an agreement can also help bring peace to Saudi Arabia, while ending Yemen’s humanitarian nightmare.
Inequitable taxation
13 Oct, 2026

Inequitable taxation

FINANCE Minister Muhammad Aurangzeb has once more reviewed the latest incentive scheme to bring retailers into the...
Taxila’s hidden past
13 Oct, 2026

Taxila’s hidden past

A HILL dismissed more than a century ago as an unremarkable heap of ruins has yielded one of Taxila’s most...