ML-1 cost more than doubled due to delay, PM told

Published June 14, 2023
Prime Minister Shehbaz Sharif chairs a meeting on Tuesday on Pakistan Railways. — Photo courtesy: PID
Prime Minister Shehbaz Sharif chairs a meeting on Tuesday on Pakistan Railways. — Photo courtesy: PID

ISLAMABAD: The cost of the ambitious Main Line-1 (ML-1) railway project has escalated more than 100 per cent due to delay in its execution, making it difficult for the government to find resources for the venture.

Now, the cost of the project, which was conceived under China Pakistan Economic Corridor (CPEC) in 2016 with an estimated cost of $6 million and financial assurance from Beijing, has gone up to $13 million.

This was informed in a meeting, presided over by Prime Minister She­­h­baz Sharif, on Pakistan Railways.

A source privy to the meeting told Dawn that the government had no financial assistance from anywhere in sight to execute the project and therefore, the premier had directed the authorities concerned to at least start the first phase of the project from Karachi to Sukkur through the government’s own resources.

Work on Karachi to Sukkur phase to be carried out using govt’s own resources

The meeting was told that China that had promised to fund the ML-1 — the project aimed at upgrade of railway track from Karachi to Peshawar — had yet to give any confirmation in this regard. The participants were further informed that the PTI government has made a dent to the project and changed the original plan ML-1 from the Built, Operate and Transfer (BOT) basis to engineering, procurement and construction (EPC) mode.

Urgent revival

According to PM Office, Prime Minister Shehbaz Sharif directed the authorities concerned for execution of ML-1 on a priority basis and said the government was working on the revival of railways on urgent basis.

“ML-1 is the backbone of Paki­stan Railways and in the future, Pakistan would provide trade corridor facilities to the regional countries through its railways and seaports systems,” the prime minister was quoted as saying.

The meeting was attended by Minister for Finance Ishaq Dar, Min­ister for Commerce Syed Naveed Qamar, Minister for Railways Khawaja Saad Rafique and others.

During the meeting, the prime minister observed that people were being facilitated through motorways, public transport, health and education initiatives completed during the PML-N tenures.

The meeting was also apprised of the ongoing reforms and digitalisation of railways. So far, the ticketing system had been completely digitalised, it was informed.

Fata-KP

Presiding over a separate meeting on development of Khyber Pakhtunkhwa in general and uplift of erstwhile Federally Admi­nistered Tribal Areas (Fata) in particular, the prime minister said: “The previous government never developed the province.”

During the meeting, the political situation of the country and various issues, including the upcoming KP assembly elections, were highlighted.

The premier said the incumbent government had taken special steps in the fiscal year 2023–24 for the development of merged tribal districts, and would ensure that the people of KP get full benefits from the health and education projects of the centre.

The PM said farmers in Khyber Pakhtunkhwa would be equipped with quality seeds, a timely supply of fertilisers and modern technology.

Published in Dawn, June 14th, 2023

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Pahalgam aftermath
24 Apr, 2026

Pahalgam aftermath

A YEAR after at least 26 people were killed in a terrorist attack in occupied Kashmir’s Pahalgam area, ties ...
Real estate power
24 Apr, 2026

Real estate power

THE latest round of land valuation revisions by the FBR for tax purposes signifies a familiar pattern that ...
Ad astra
Updated 24 Apr, 2026

Ad astra

AMONG the many developments this month that Pakistanis can take pride in is the news that one of their own will soon...
Ceasefire extension
Updated 23 Apr, 2026

Ceasefire extension

THOUGH the US has extended the Iran ceasefire — thanks largely to effective Pakistani diplomacy to prevent sliding...
Climate & livelihoods
23 Apr, 2026

Climate & livelihoods

THE latest ILO report estimates that around 3.3m jobs may have been affected by the 2025 floods — significantly...
Virtual courts
23 Apr, 2026

Virtual courts

THOUGH routine activities in Islamabad have been greatly hindered amidst security preparations for another round of...