ISLAMABAD: Amid an eight-month delay to the Mohmand Dam completion because of flood damages, the Senate Standing Committee on Planning and Development on Thursday sought an end to public procurement rules to ensure ‘quality projects in the country instead of low-cost projects.

Presided over by Senator Atta ur Rehman, the Senate panel was informed that over $1.5 billion worth of Mohmand Dam’s structure had been damaged by recent floods, resulting in a project delay of about eight months. Officials of the Planning Division said both tunnels of the dam were marred by land sliding and some other under-construction parts of the project also got damaged.

The meeting was informed that the prime minister had appointed a five-member fact-finding committee to probe the losses to the dam. The committee comprised local and international experts in relevant fields. The team had already visited the project and would soon be submitting a report to the prime minister.

The committee was informed that once completed the dam will help regulate floods, thus mitigating the risk of flooding in low-lying areas in Charsadda, Peshawar and Nowshera districts.

During a briefing on amendments to Public Procurement Regulatory Authority (PPRA) rules, the committee was informed that rules would ensure maximum transparency and efficiency as PPRA had been continually trying to remove all unnecessary hurdles in the way of development projects.

The committee was along with the lowest bid, the new rules also required standards to be the key determining factor for the award of new contracts for development projects.

The members of the committee stressed the need for doing away with PPRA rules as the country needed quality projects instead of low-cost projects.

The committee unanimously agreed to the proposal and recommended that a meeting with the prime minister should be arranged so that further transparency and improvements are introduced in awarding contracts for various development projects.

During discussions on foreign aid for flood relief activities, the Planning Com­mission officials denied that the IMF expressed reservations about estimates of flood losses in Pakistan.

Published in Dawn, December 2nd, 2022

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Weathering the storm
Updated 29 Apr, 2024

Weathering the storm

Let 2024 be the year when we all proactively ensure that our communities are safeguarded and that the future is secure against the inevitable next storm.
Afghan repatriation
29 Apr, 2024

Afghan repatriation

COMPARED to the roughshod manner in which the caretaker set-up dealt with the issue, the elected government seems a...
Trying harder
29 Apr, 2024

Trying harder

IT is a relief that Pakistan managed to salvage some pride. Pakistan had taken the lead, then fell behind before...
Return to the helm
Updated 28 Apr, 2024

Return to the helm

With Nawaz Sharif as PML-N president, will we see more grievances being aired?
Unvaxxed & vulnerable
Updated 28 Apr, 2024

Unvaxxed & vulnerable

Even deadly mosquito-borne illnesses like dengue and malaria have vaccines, but they are virtually unheard of in Pakistan.
Gaza’s hell
Updated 28 Apr, 2024

Gaza’s hell

Perhaps Western ‘statesmen’ may moderate their policies if a significant percentage of voters punish them at the ballot box.