NTDC fined Rs50m for nationwide blackout

Published
0
In this file photo, LESCO staff install a transformer. The country faced a shortfall of 6,000 to 7,000MW in the last week of April. Urban areas experience six to 10 hours, rural parts witness eight to 16 hours of loadshedding.—APP
In this file photo, LESCO staff install a transformer. The country faced a shortfall of 6,000 to 7,000MW in the last week of April. Urban areas experience six to 10 hours, rural parts witness eight to 16 hours of loadshedding.—APP

ISLAMABAD: The National Electric Power Regulatory Authority (Nepra) on Friday imposed a fine of Rs50 million on the National Transmission & Despatch Company (NTDC) for its failure to restore power supply in a timely manner following a nationwide power system collapse on January 9 last year. Following the blackout, it took 20 hours to restore the system.

In an order issued here, the regulator said it had taken serious notice of the January 9, 2021, incident of massive power breakdown and had constituted an inquiry committee to thoroughly investigate the matter in the light of Nepra’s Laws, Rules and Regulations. The committee conducted the inquiry and presented a detailed report to the five-member Nepra which initiated legal proceedings against the NTDC on the basis of the report.

It said an explanation was called from NTDC – the national grid operator – on April 1, 2021 on the basis of the inquiry report under Rule 4(1) of the Nepra (Fines) Rules 2002. This was followed by a show cause notice to the system operator on August 25, 2021, under Section 27B of the Nepra Act.

The regulator said it also provided an opportunity of hearing to NTDC on January 12, 2022, but it “failed to provide any satisfactory response and was found guilty of violating relevant provisions of the Grid Code,” hence the Rs50m fine. The regulator said it had also initiated legal proceedings against concerned power plants for their lapses, deficiencies and failures in the said breakdown, which were currently under process and being dealt with separately.

Interestingly, a separate internal inquiry committee of the NTDC had absolved the NTDC of any fault and had blamed staff of Guddu Power Company. “No NTDC’s officer/official has been found negligent for discharge of his duties, as the event which initiated this widespread breakdown was not in NTDC’s system, rather it was in the 220kv switchyard of Guddu Old Thermal Power Station under the control of CPGCL (Central Power Generation Company Limited),” said the NTDC’s inquiry report.

Published in Dawn, May 7th, 2022

Opinion

Editorial

Restructuring plans
Updated 29 Oct, 2026

Restructuring plans

The primary reason for governance failure in Pakistan is not the geographical size of the existing provinces but the reluctance of provincial capitals to empower local bodies.
Polluted priorities
Updated 29 Oct, 2026

Polluted priorities

Enforcement must continue, but decisions should follow evidence, not the visibility of machinery on city roads.
Continuing genocide
29 Oct, 2026

Continuing genocide

FOR the people of Gaza, despite the ‘ceasefire’ reached last October, the genocide never really ceased. This ...
Regional security
Updated 28 Oct, 2026

Regional security

Iran and the Makkah pact states should pledge not to let external actors use their soil to launch aggression against each other.
Rate hike
28 Oct, 2026

Rate hike

THE SBP’s decision to raise its policy rate by 50 basis points to 12pc was largely expected. It is also justified...
Press solidarity
28 Oct, 2026

Press solidarity

PAKISTAN’S journalists have seldom lacked organisations speaking in defence of press freedom. What has been ...