88pc work on first CPEC hydropower project completed: Asim Bajwa

Published May 12, 2021
A view of the Karot Hydropower Project being built on the River Jhelum. — Photo courtesy Asim Bajwa Twitter
A view of the Karot Hydropower Project being built on the River Jhelum. — Photo courtesy Asim Bajwa Twitter
The Karot Hydropower Project is expected to be completed in April 2022. — Photo courtesy Asim Bajwa Twitter
The Karot Hydropower Project is expected to be completed in April 2022. — Photo courtesy Asim Bajwa Twitter

Chairman of the China-Pakistan Economic Corridor (CPEC) Authority Asim Saleem Bajwa shared on Wednesday that 88 per cent of the work on the Karot Hydropower Project has been completed.

The hydropower project — the first of its kind under the CPEC — is expected to be completed in April 2022 and is being built on the River Jhelum, he said.

Sharing the details of the Karot Hydropower Project in a tweet, Bajwa said the investment in it amounted to $1,780 million while 5,000 local people were directly employed for its construction.

The 720-megawatt Karot Hydropower Project was initially due to be completed in 2020. It has the capability to generate 3.249 billion units of clean electricity per year for the national grid.

Read | CPEC 2.0: full speed ahead

The project is being developed on a Build-Own-Operate and Transfer (BOOT) basis at an estimated cost of $1.98bn including a development cost of $1.698bn and interest during construction of $243m by Karot Power Company Private Ltd, comprising of M/s Three Gorges South Asia Investment Ltd (TGSAIL) and Associated Technologies (Pvt) Ltd of Pakistan.

The project is being constructed on a concrete gravity of 91 metres high dam with a crest length of 320 meters near the village of Gohra. The dam's reservoir will be approximately 152m cubic metres in volume, with a length of 27 kilometres. Around 72 homes and 58 businesses were expected to be relocated due to project construction while 2.8-km of the Karot-Kotli road and 8.9-km of the Azad Pattan-Kahuta road were expected to need relocation.

The National Electric Power Regulatory Authority (Nepra) had approved in February 2016 the project's levelised tariff at 7.57 cents per unit for 30 years at an exchange rate of Rs101.6 per dollar. Its groundbreaking ceremony was held in January of that year.

Opinion

Editorial

Punishing evaders
02 May, 2024

Punishing evaders

THE FBR’s decision to block mobile phone connections of more than half a million individuals who did not file...
Engaging Riyadh
Updated 02 May, 2024

Engaging Riyadh

It must be stressed that to pull in maximum foreign investment, a climate of domestic political stability is crucial.
Freedom to question
02 May, 2024

Freedom to question

WITH frequently suspended freedoms, increasing violence and few to speak out for the oppressed, it is unlikely that...
Wheat protests
Updated 01 May, 2024

Wheat protests

The government should withdraw from the wheat trade gradually, replacing the existing market support mechanism with an effective new one over the next several years.
Polio drive
01 May, 2024

Polio drive

THE year’s fourth polio drive has kicked off across Pakistan, with the aim to immunise more than 24m children ...
Workers’ struggle
Updated 01 May, 2024

Workers’ struggle

Yet the struggle to secure a living wage — and decent working conditions — for the toiling masses must continue.