ISLAMABAD: The Pakistan Atomic Energy Commission (PAEC) on Tuesday announced it had achieved criticality of its 1,100MW nuclear power station in Karachi, one of the two major nuclear plants in the city.

The commission said the 1,100MW plant, called K-2, would go through certain safety tests and procedures before it is connected to the national grid by the end of March.

K-2 is one of the two similar under-construction nuclear power plants (NPPs) located near Karachi and will be inaugurated for commercial operation by the end of May this year. The other one, K-3, is expected to become operational in 2022.

K-2 is the first nuclear power plant in Pakistan with a generation capacity of over 1,000MW and will help reduce loadshedding in summers by generating environment friendly, affordable and reliable base load electricity for the country.

The PAEC was previously running five NPPs in the country (one at Karachi and four at Chashma) with collective generation capacity of nearly 1,400MW. Therefore, the K-2 would almost double the capacity of the country’s NPPs, improving considerably the share of nuclear power in the overall energy mix.

The loading of nuclear fuel onto the plant was started on December 1 last year after clearance from the Pakistan Nuclear Regulatory Authority. The PAEC had at the time announced that it would achieve COD commercial operations of K-2 in April 2021 and that of K-3 by the end of 2021.

On Tuesday, the PAEC spokesperson said that the first plant was expected to reach COD by the end of May and the K-3 in 2022.

Published in Dawn, March 3rd, 2021

Opinion

Trouble in Camelot
Updated 06 May 2021

Trouble in Camelot

The electorate knows better than to swallow the government’s rhetoric.
Time to wake up
Updated 05 May 2021

Time to wake up

The criticism reflects our failure to counter rising religious intolerance and bigotry, and also exposes a diplomatic debacle.

Editorial

Proceed with caution
Updated 06 May 2021

Proceed with caution

The slightest loosening of SOP protocols could send us hurling in the direction where India finds itself today.
06 May 2021

IPP dues

THE ECC decision to pay the first tranche of outstanding dues of one set of IPPs, and further delay the payments of...
06 May 2021

Violence against doctors

HEALTHCARE workers and doctors’ associations in two major hospitals of KP are adamant that the KP Healthcare...
05 May 2021

Path of growth

FINANCE MINISTER Shaukat Tarin finally specified the future direction that the country’s economic policy will take...
05 May 2021

Human rights 2020

THE human rights situation in Pakistan, almost predictably bleak every year, was deeply impacted in 2020 by an...
Unreasonable behaviour
Updated 05 May 2021

Unreasonable behaviour

Usman Buzdar should reprimand Dr Awan for her coarse behaviour and make sure she tenders a public apology.