MIANWALI: The mega project of dualisation of road between Sargodha and Mianwali is being delayed due to alleged lack of cooperation among various departments.

The project being in the hometown of the prime minister was inaugurated by him in January 2020. The work for Phase-I is scheduled to be completed in June 2021.This road starts from Mianwali towards Sargodha as the Phase-I covers the distance of 30.63 kilometres, It is estimated to be completed at a cost of Rs4,700 million.

In addition to that, the Highways Department has paid huge amounts to the Pakistan Railways, Wapda and forest department. The Pakistan Railways got Rs32.50 million to widen the only level crossing at Wan-Bhachran.

The road has been completed on both sides but the level crossing has not been widened. Wapda has got Rs22.50 million to replace electricity poles from the roadside and they are still unmoved.

The Punjab government has not yet included funds in the current budget for the phase-II & III of the project falling in the limits of Khushab and Sargodha.

Contractor Mian Mohammad Khan told Dawn that he had nearly completed work on both sides of the level crossing at Wan-Bachran and his labour would sit idle till the widening of the railway crossing.

Executive Engineer Highways Mianwali Mr Mansoor Arshad Pansota said his department made payments to the Pakistan Railways and Wapda authorities at the start of the project but despite persistent reminders by him, both departments were not cooperating.

Published in Dawn, February 27th, 2021

Opinion

Editorial

Lull in fighting
Updated 28 Jul, 2026

Lull in fighting

AFTER two weeks of escalating violence, the US has halted its strikes on Iran, with Tehran also silencing it guns....
Water policy
28 Jul, 2026

Water policy

THE country is caught in a crisis where there too much water at the wrong time and too little when it is most ...
Ending hepatitis
28 Jul, 2026

Ending hepatitis

WORLD Hepatitis Day is being observed under the theme ‘Hepatitis: Let’s break it down’, a call to remove the...
Writing on the wall
27 Jul, 2026

Writing on the wall

EVERY few months, another set of figures reminds Pakistan of a painful reality. Sahil’s latest Six Months Cruel...
Still unprepared
27 Jul, 2026

Still unprepared

EVEN as Pakistan counts around 100 deaths since the onset of the monsoon season on June 26, it is bracing for ...
Delayed devolution
27 Jul, 2026

Delayed devolution

THE debate over Islamabad’s reluctance to fully let go of devolved subjects has been running since 2010. But it ...