LAHORE: The fourth and last unit of the Neelum-Jhelum Hydropower Project (NJHP) was synchronised with national grid on Monday after it started generating over 200 megawatts on a trial basis.

During the project’s trial run, the unit will be tested on various loads ranging up to 242MW.

“With successful commissioning of its all four units, the NJHP is expected to attain its installed generation capacity of 969MW in a couple of days,” said a spokesperson for the Water and Power Development Authority.

Three units at the project have already been generating 726MW of electricity on trial basis; thus far, they have contributed around 900 million electricity units to the national grid.

It may be recalled that commercial operation of fourth unit at NJHP was delayed in May after experts identified some technical issues in the machine during various tests and sought replacement for some parts.

This unit had actually started trial generation in April and later went through various tests required for commercial operation. The unit injected more than 1.3m units of electricity during test run.

However, while testing the unit, the ‘run-outs’ exceeded specifications. Therefore, project consultants concluded that in order to smoothly operate the unit for its designated life, its parts — ‘labyrinth’ and ‘lower sleeve’ — should be replaced with new ones.

Published in Dawn, August 14th, 2018

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

After the budget
Updated 26 Jun, 2026

After the budget

Though not a bad document per se, the budget for FY27 is a familiar one, and familiarity in our economic history is rarely cause for comfort.
Missing the mark
Updated 27 Jun, 2026

Missing the mark

Pakistan cannot rely on international partners to compensate for weak governance and inconsistent implementation at home.
Up in smoke
26 Jun, 2026

Up in smoke

PAKISTAN is watching an epidemic unfold as the menace of narcotic abuse hits every fourth household in Karachi ...
Reflection time
Updated 25 Jun, 2026

Reflection time

Israel is the biggest source of instability in the Middle East, and it is high time the US ended its blind support to Tel Aviv, if it genuinely wants peace in the region.
Raised temperatures
25 Jun, 2026

Raised temperatures

THE fraught situation in Azad Jammu and Kashmir requires immense patience and cool heads. Temperatures are raised on...
Debatable remedy
25 Jun, 2026

Debatable remedy

THE Pakistan Psychiatric Society’s challenge to the Federal Shariat Court’s ruling on attempted suicide deserves...