The Peshawar High Court (PHC) on Wednesday ordered the National Accountability Bureau (NAB) to probe the Peshawar Sustainable Bus Rapid Transit Corridor (BRT) Project, which it termed "shady and shaky".

The high court issued the detailed order almost seven months after it had allowed the authorities to continue to work on the project but submit reports on the project's progress.

"After hearing the arguments at great length, we feel it's appropriate to refer the matter to NAB authorities for conducting proper investigation due to the fact that 50 per cent scope of the work has been enhanced," the court order stated.

The PHC, in its detailed verdict, observed that the BRT project was awarded to a firm that was blacklisted in another province, and that the project stood incomplete as of June 24.

"The delay, the contract awarding process, feasibility and all the issues relating to the Peshawar Sustainable Bus Rapid Transit Corridor (BRT) Project are all shady and shaky," the order said.

Moreover, the court noted that the project was initially projected to cost Rs49.3bn but the figures eventually soared to Rs67.9 billion.

"We have been informed that from different necessary project schemes, the amount has been allocated for this project without considering the fact that other projects were also necessary and important for public purpose," the verdict adds.

The court directed the NAB authorities to complete their probe and submit its findings in the next hearing, scheduled to he held on September 4.

Opinion

Editorial

X post facto
Updated 19 Apr, 2024

X post facto

Our decision-makers should realise the harm they are causing.
Insufficient inquiry
19 Apr, 2024

Insufficient inquiry

UNLESS the state is honest about the mistakes its functionaries have made, we will be doomed to repeat our follies....
Melting glaciers
19 Apr, 2024

Melting glaciers

AFTER several rain-related deaths in KP in recent days, the Provincial Disaster Management Authority has sprung into...
IMF’s projections
Updated 18 Apr, 2024

IMF’s projections

The problems are well-known and the country is aware of what is needed to stabilise the economy; the challenge is follow-through and implementation.
Hepatitis crisis
18 Apr, 2024

Hepatitis crisis

THE sheer scale of the crisis is staggering. A new WHO report flags Pakistan as the country with the highest number...
Never-ending suffering
18 Apr, 2024

Never-ending suffering

OVER the weekend, the world witnessed an intense spectacle when Iran launched its drone-and-missile barrage against...