GUJRANWALA: When the government had approved the the construction of a district government’s parking plaza on GT Road in Gujranwala in 2014, its estimated cost was Rs270 million.

As the construction was done at a slow pace, the 11-storey plaza is still incomplete and now its cost has increased to Rs490 million, according to reports.

The city district government started construction of the parking plaza to facilitate the vehicle owners, and it was to be built in one year (2015). The first two storeys were for offices and shops and the remaining nine for the parking of vehicles.

The plaza was to be ready by March 30, 2015, but its deadline was extended to March 30, 2016.

The delay increased estimated cost from Rs270 million to Rs490 million.

District Coordination Officer Muhammad Aamir Jan ordered an inquiry into the delay, but the inquiry report is also suffering delays.

Published in Dawn, April 27th, 2016

Opinion

Editorial

Punishing evaders
02 May, 2024

Punishing evaders

THE FBR’s decision to block mobile phone connections of more than half a million individuals who did not file...
Engaging Riyadh
Updated 02 May, 2024

Engaging Riyadh

It must be stressed that to pull in maximum foreign investment, a climate of domestic political stability is crucial.
Freedom to question
02 May, 2024

Freedom to question

WITH frequently suspended freedoms, increasing violence and few to speak out for the oppressed, it is unlikely that...
Wheat protests
Updated 01 May, 2024

Wheat protests

The government should withdraw from the wheat trade gradually, replacing the existing market support mechanism with an effective new one over the next several years.
Polio drive
01 May, 2024

Polio drive

THE year’s fourth polio drive has kicked off across Pakistan, with the aim to immunise more than 24m children ...
Workers’ struggle
Updated 01 May, 2024

Workers’ struggle

Yet the struggle to secure a living wage — and decent working conditions — for the toiling masses must continue.