KARACHI, Nov 17: Differences between the city government and the contractors might further delay the reconstruction of Mubarak Dam.

The project has already suffered delays due to non-release of funds by the Sindh government in the past.

The city government is trying its best to convince the contractors to resume work, but the contractors are not willing to resume work on old rates and unless the CDGK pays the outstanding the amount.

The city government had refused to pay the outstanding dues arguing that the Sindh government was not releasing the funds but when it released the funds, the city government has put conditions.

Construction of the Mubarak Dam, which washed away in recent rain, began one-and-a-half years back but later on halted due to denial of funds by the Sindh government, sources said.

The city Nazim, Naimatullah Khan, along with journalists and the city government officials, had visited the fishermen’s village (site of the dam) on July 18 and assured the people that work would restart within 15 days.

Walls of the under-construction dam had collapsed during the recent rains causing a massive mudslide.

The area people have still been waiting to see the development work on the reconstruction of dam, provision of electricity and building of link road as per promises made by the Nazim.

The project was to be completed in nine months and was being funded by the World Bank but due to irresponsive approach by the government officials, the project is still incomplete.—PPI

Opinion

Editorial

GB polls’ aftermath
Updated 11 Jun, 2026

GB polls’ aftermath

The new administration must address the region’s issues proactively.
Peace in retreat
11 Jun, 2026

Peace in retreat

THE ceasefire announced in April was supposed to create space for negotiations. Instead, it has been repeatedly...
A few good men
11 Jun, 2026

A few good men

IT was a brave move, no doubt. This Tuesday, in the land of the Afghan Taliban, a few good men decided to take a...
Centre vs provinces
Updated 10 Jun, 2026

Centre vs provinces

The reason the centre finds itself in this position is rooted in its failure to expand the tax net and boost revenues.
Party in crisis
10 Jun, 2026

Party in crisis

THE young KP chief minister must be starting to realise just how thorny a seat he occupies. There has been a flurry...
Varsity woes
10 Jun, 2026

Varsity woes

FINANCIAL crises affecting public sector universities across Pakistan are now having an impact on academic...