RAWALPINDI: Fog and biting cold have forced the contractors of metro bus project to stop work during the night.

However, Rawalpindi Development Authority (RDA) on Monday asked the contractors to increase the labour force in the day to complete work by December 30.

During a visit to the construction site, Commissioner Zahid Saeed was informed that the labourers would not be able to work at night and early morning due to thick fog.

The commissioner inspected Package-I (Faizabad to 9th Avenue) in Islamabad and Package-II (Peshawar Mor) and asked the contractors to complete work by December 30 so that finishing touches could be given to the project.

He said the corridor for metro bus from Faizabad to Peshawar Mor was almost complete, adding that the weather would improve in the next two days and contractors would speed up work.

Published in Dawn, December 23rd, 2014

Opinion

Editorial

Border clashes
19 May, 2024

Border clashes

THE Pakistan-Afghanistan frontier has witnessed another series of flare-ups, this time in the Kurram tribal district...
Penalising the dutiful
19 May, 2024

Penalising the dutiful

DOES the government feel no remorse in burdening honest citizens with the cost of its own ineptitude? With the ...
Students in Kyrgyzstan
Updated 19 May, 2024

Students in Kyrgyzstan

The govt ought to take a direct approach comprising convincing communication with the students and Kyrgyz authorities.
Ominous demands
Updated 18 May, 2024

Ominous demands

The federal government needs to boost its revenues to reduce future borrowing and pay back its existing debt.
Property leaks
18 May, 2024

Property leaks

THE leaked Dubai property data reported on by media organisations around the world earlier this week seems to have...
Heat warnings
18 May, 2024

Heat warnings

STARTING next week, the country must brace for brutal heatwaves. The NDMA warns of severe conditions with...