Cost of Nandipur Power Project skyrockets to Rs84 billion

Published
11

ISLAMABAD: Amid heavy criticism, the cost of the Rs27 billion Nandipur Power Project is now a staggering Rs84bn, making it the most expensive power project in Pakistan.

A copy of official documents, available with DawnNews, show that the cost of Nandipur Power Project has gone up from Rs57bn to reach Rs84bn. According to the PC-I of the project, the original cost was set at Rs22bn. However, due to a delay of seven years in the completion of the project, the cost went up. The PML-N government then revised the cost during 2013, jacking it up by Rs35bn and fixing it at Rs57.4bn.

When contacted by DawnNews, Managing Director Nandipur Power Project Muhammad Mehmood, expressed surprise about the increase in cost.

He further said that he was unable to respond at the moment as to how National Electric Power Regulatory Authority (Nepra) had determined the project cost at Rs84bn.

According to the MD, cost of the project currently stands at Rs57billion.

It merits mentioning here that official documents detailing the project cost was forwarded to Nepra after the necessary alleged approval of the MD.

However, Mehmood said he was unaware about the actual cost, which was mentioned on page 13 of the official document.

 Image of project cost in document
Image of project cost in document

The document states that Engineering, Procurement and Construction (EPC) cost and related cost was $502.318m, Taxes & Duties $21.773m, Emergency Spare parts $ 15.00m, O&M Mobilisation $5.00m, Non-EPC Construction $56.750m, Financial Fees & Charges $16.838, Interest during Construction (IDC) $229.491million. In this way, the total cost stands at $847.016million.

Recently, the Northern Power Generation Company (NPGC) had sought approval from Nepra to fix the power tariff of the project for 30 years at Rs18.16 per unit with furnace oil, Rs27.91/unit with high speed diesel (HSD) and Rs8.44/unit with gas.

Sources in the water and power ministry said Nepra, the power sector regulator, was perturbed over the increase in project cost and its tariff rate.

Sources said few members and officials of the authority were upset by the said raises in tariff and cost of the power project and were not in favour to pass on the additional burden to the power consumers.

On finding a plea from NPGC, Nepra in a bid to approve tariff in the light of stakeholder’s opinion/comments has advertised 13 questions and sent them to all stake holders including ministries of power, finance, planning, Sui Southern Gas Company Limited, Sui Northern Gas Pipelines Limited, Consumers Protection Associations etc.

Opinion

Editorial

Restructuring plans
Updated 29 Oct, 2026

Restructuring plans

The primary reason for governance failure in Pakistan is not the geographical size of the existing provinces but the reluctance of provincial capitals to empower local bodies.
Polluted priorities
Updated 29 Oct, 2026

Polluted priorities

Enforcement must continue, but decisions should follow evidence, not the visibility of machinery on city roads.
Continuing genocide
29 Oct, 2026

Continuing genocide

FOR the people of Gaza, despite the ‘ceasefire’ reached last October, the genocide never really ceased. This ...
Regional security
Updated 28 Oct, 2026

Regional security

Iran and the Makkah pact states should pledge not to let external actors use their soil to launch aggression against each other.
Rate hike
28 Oct, 2026

Rate hike

THE SBP’s decision to raise its policy rate by 50 basis points to 12pc was largely expected. It is also justified...
Press solidarity
28 Oct, 2026

Press solidarity

PAKISTAN’S journalists have seldom lacked organisations speaking in defence of press freedom. What has been ...