Power grid can’t cope with demand

Published
13

ISLAMABAD: The authorities conceded on Thursday that due to obsolete transmission system the national grid was simply incapable of supplying more than 15,000MW of electricity to consumers.

They also acknowledged that they were resorting to 25-30 per cent of loadshedding at the time of Sehr and Iftar.

  Water and Power Secretary Nargis Sethi
Water and Power Secretary Nargis Sethi

Water and Power Secre­tary Nargis Sethi told the National Assembly’s Stand­ing Committee on Water and Power that the transmission system was incapable of sustaining a supply of more than 15,000MW, as overloading led to tripping and other serious problems.

“In case the load exceeds 15,000MW, it seems the entire system has been put on fire,” she remarked during the meeting.


25-30pc of loadshedding being done at Sehr and Iftar timings


Ms Sethi said the system needed to be upgraded fast. Efforts should also be made to improve the rate of recovery of dues.

She, however, urged the committee led by Arshad Khan Leghari to bear with the current team of power managers because “we will give positive results soon”.

State Minister Abid Sher Ali admitted that people were forced to endure electricity shortage of between 25 and 30 per cent at the time of Sehr and Iftar. At these times the demand rose to 20,000MW but the transmission system could not supply more than 15,000MW.

The minister said that in an effort to control theft, 100,000 electricity meters had been changed in Lahore on the directives of the prime minister.


Related: Power subsidy being increased in Ramazan


The committee also reviewed the steps taken to control power theft during the tenure of former chief executive of the Lahore Electric Supply Company (Lesco) Arshad Rafique. Lesco chief Rao Zamir­uddin said that 4,234 first information reports were registered during the tenure of Mr Rafique and 58,365 detection bills of Rs1.6 billion sent out. So far Rs685 million had been recovered.

Answering a question, Abid Sher Ali said it had become “impossible” for the government to provide electricity to tube wells at Rs10.34 per unit. The rate would have to be increased by up to Rs2 per unit.

He said the government was providing subsidy to farmers through other means, including schemes for cheaper tractors and fertilisers. He said the government was trying to complete power generation projects at the earliest so that electricity shortage could be overcome.

To a question, Ms Sethi confirmed that there was a shortage of electricity transformers because of some pending cases in courts but the government was trying to overcome the problem.


Also read: Extended blackouts during Ramazan feared


Published in Dawn, July 4th, 2014

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Governance test
15 Aug, 2026

Governance test

EVER since the interior minister called for smaller administrative units to improve governance, the question of new...
Sailors’ killing
15 Aug, 2026

Sailors’ killing

THE killing of at least three Pakistani sailors in an apparent Houthi attack targeting a vessel in the waters of Bab...
Lethal celebrations
15 Aug, 2026

Lethal celebrations

IT is a familiar tale. Every year, occasions for national celebration turn into fear and mourning just because some...
Taliban support
Updated 14 Aug, 2026

Taliban support

THE latest UN monitoring report analysing the activities of several transnational terrorist groups is unequivocal in...
Job policy for youth
14 Aug, 2026

Job policy for youth

STRIPPED of its rhetoric, the prime minister’s announcement of Pakistan’s first National Youth Employment Policy...
Jail improvements
14 Aug, 2026

Jail improvements

THE Punjab government is spending Rs5bn on modernising jail facilities in the province, but to what end? The...