PESHAWAR, Oct 24: A 132kv grid station will be set up at Ghalanai, Mohmand Agency, and funds for the project would come from the Federally Administered Tribal Areas' annual development programme for 2004-05.

According to a press release issued here on Sunday by the Tribal Electricity Supply Company, the cost of the project is Rs165 million.

On the pursuance of NWFP Governor Syed Iftikhar Hussain Shah, funds for the project would be provided from the ADP, it said.

The project, expected to be completed by June, 2005, includes establishment of the grid station, laying of 25km of transmission line and erection of 90 High-power transmission line towers.

Currently, two 66kv grid stations supply electricity to parts of the agency.

The project would help overcome problems of low voltage, which force the company to take recourse to load management, the release said.

Opinion

Editorial

GB polls’ aftermath
11 Jun, 2026

GB polls’ aftermath

IT appears that the PPP is in a comfortable position to form the government in Gilgit-Baltistan after Sunday’s...
Peace in retreat
11 Jun, 2026

Peace in retreat

THE ceasefire announced in April was supposed to create space for negotiations. Instead, it has been repeatedly...
A few good men
11 Jun, 2026

A few good men

IT was a brave move, no doubt. This Tuesday, in the land of the Afghan Taliban, a few good men decided to take a...
Centre vs provinces
Updated 10 Jun, 2026

Centre vs provinces

The reason the centre finds itself in this position is rooted in its failure to expand the tax net and boost revenues.
Party in crisis
10 Jun, 2026

Party in crisis

THE young KP chief minister must be starting to realise just how thorny a seat he occupies. There has been a flurry...
Varsity woes
10 Jun, 2026

Varsity woes

FINANCIAL crises affecting public sector universities across Pakistan are now having an impact on academic...