LAHORE, May 23: Work on various components of the Greater Thal Canal, one of Wapda’s Vision 2025 projects, is on schedule or ahead, Engr Mumtaz Husain Sheikh, the project director has said.

Engr Sheikh was speaking to a group of journalists from Lahore. Wapda had arranged the visit.

Project officials hoped that the momentum would continue and the canal would be completed by June 30, 2007, if not earlier.

Not is time overrun the only frequent development project problem the Wapda hopes to avert. Cost overrun is another. Estimated at Rs61 billion in the initial Vision documents, the cost approved by the Executive Committee of the National Economic Council is Rs30.467 billion. While it is too early in the project life to predict that the trend can sustain itself, the project director stated with some satisfaction that the two earth-moving contracts granted so far, had both been for amounts substantially below the original estimates. The cost for the first five-kilometre stretch had been nearly 25 per cent below the Rs20 million estimate. The second component, a 15-kilometre stretch, had been contracted at 49 per cent below the Rs40 million estimate. The project director attributed low rates to fiercely competitive bidding. For its part, Wapda has decided not to purchase the Rs70 million vehicles, approved for the project and make do with vehicles made available from other projects.

The project director said the local administration and the Irrigation and Power Department, which is incharge of land acquisition, had so far given his team no trouble. Early on, he said, the local people had expressed apprehensions of water logging. Once they were informed that the 35-kilometre main canal, as well as 342-kilometre branches were to be concrete-lined, they had not objected to it. Fortunately, he said, no major resettlement was involved.

On completion, the project is meant to serve 1.92 million acres of land in Khushab, Bhakkar, Leiah and Jhang districts between Thal and Rangpur Canals during Kharif season. The average benefit to farmers is expected to be Rs4,790 per acre. The improved farming is expected to supplement government revenue by Rs45 million a year. Water rate (abiyana) is proposed to be charged at Rs92 per acre).

TELEMETRY: Earlier, at a briefing on telemetry at Chashma Barrage, he said installation of telemeters at Chashma and Trimmu Barrages had provided a valuable means of additional verification on operation of barrages and water resource situation in the country.

He also said tenders for installation of telemeters at 21 measurement stations would be opened on July 1. The Rs450 million project, he said, was expected to be completed within a year.

Replying to questions on the occasion, the executive engineer incharge claimed that the system was fool-proof. Currently, he said, the data was relayed to Baddoke near Lahore from where it was routed to irrigation as well as flood warning and control authorities. He said there had been no maintenance problems in eight years of the system’s operation.

Opinion

Editorial

GB polls’ aftermath
11 Jun, 2026

GB polls’ aftermath

IT appears that the PPP is in a comfortable position to form the government in Gilgit-Baltistan after Sunday’s...
Peace in retreat
11 Jun, 2026

Peace in retreat

THE ceasefire announced in April was supposed to create space for negotiations. Instead, it has been repeatedly...
A few good men
11 Jun, 2026

A few good men

IT was a brave move, no doubt. This Tuesday, in the land of the Afghan Taliban, a few good men decided to take a...
Centre vs provinces
Updated 10 Jun, 2026

Centre vs provinces

The reason the centre finds itself in this position is rooted in its failure to expand the tax net and boost revenues.
Party in crisis
10 Jun, 2026

Party in crisis

THE young KP chief minister must be starting to realise just how thorny a seat he occupies. There has been a flurry...
Varsity woes
10 Jun, 2026

Varsity woes

FINANCIAL crises affecting public sector universities across Pakistan are now having an impact on academic...