ISLAMABAD: The National Electric Power Regulatory Authority (Nepra) on Wednesday directed K-Electric (KE) and other distribution companies (Discos) to refund Rs4.035 and 50 paise per unit, respectively, to consumers for overcharging in April and May.

The decision was made in response to requests from the Power Division, which had sought to cap the negative fuel adjustment for KE at Rs4 per unit for April and impose an additional 10 paise per unit on Discos’ consumers for May. Nepra rejected both proposals.

In KE’s case, Nepra ruled that the Power Division lacked the legal standing to request deferral or rejection of fuel cost adjustments without formal approval from the prime minister and the federal cabinet.

For Discos, Nepra approved a negative fuel charge adjustment of 50 paise per unit for electricity consumed in May, based on pending adjustments of independent power producers (IPPs) in consultation with the Central Power Purchasing Agency (CPPA).

Nepra orders KE to refund Rs4.03 and Discos 50 paise for overcharging in April and May

Both refunds — Rs4.035 per unit for KE and 50 paise per unit for Discos — will be reflected in consumer bills for July.

On a separate note, Nepra Member (Technical) from Sindh, Rafique A. Shaikh, highlighted that systemic inefficiencies and mismanagement had added a financial burden of over Rs170 billion on consumers during FY25. He cited the underutilisation of the Matiari-Lahore transmission line and delays in KE’s integration with the national grid as key contributing factors.

Mr Shaikh pointed out that multiple unresolved issues had been affecting the power sector for several months, particularly in monthly fuel charges, without any meaningful improvement.

The prolonged forced outage of the Guddu 747MW steam turbine alone resulted in losses of Rs116bn ($412.81 million) in FY25. Partial Load Adjustment Charges (PLAC) added another Rs37.2bn ($132.41m), exacerbating financial stress for consumers.

Despite full-capacity payments, utilisation of the high-voltage direct current (HVDC) transmission line remained low — averaging just 40pc (1,600MW) — signalling inefficiencies and wastage of system capacity. Additional avoidable losses due to system constraints pushed the cumulative financial impact to Rs13.86bn ($49.33m) for the year.

Published in Dawn, July 10th, 2025

Opinion

Editorial

Real FBR reform
21 Oct, 2026

Real FBR reform

REFORM of the FBR has always been easier to promise than to deliver. Since the late 1990s, governments have tried...
Missing lawmakers
21 Oct, 2026

Missing lawmakers

FOLLOWING the imposition of emergency and governor’s rule in KP on Oct 11, many lawmakers of the PTI remain...
Tackling rabies
21 Oct, 2026

Tackling rabies

RABIES is a deadly but preventable zoonotic disease. On Monday, two more victims succumbed to it in Sindh, taking ...
Burnt bridges
Updated 20 Oct, 2026

Burnt bridges

If PPP wants the decision reversed, it should convince its ally in Islamabad, not ask the opposition to be ‘positive’.
Toll on trade
Updated 20 Oct, 2026

Toll on trade

Islamabad must find the right balance between its security priorities and the economic strain on KP’s residents.
French protests
20 Oct, 2026

French protests

SEVERAL European states have witnessed mass protests over the past few days, mostly focusing on socioeconomic...