No further extension in Sukkur Barrage rehabilitation project: WB official

Published November 3, 2023
WORLD Bank officials, in the front row, listen to chief engineer of Sukkur Barrage.—Photo by the writer
WORLD Bank officials, in the front row, listen to chief engineer of Sukkur Barrage.—Photo by the writer

SUKKUR: World Bank’s water resources management specialist Theruni Liyanage has urged the need to complete rehabilitation and modernisation of Sukkur Barrage in its stipulated period of four years, clearly stating that no further extension will be granted.

She was part of the World Bank Implemention Support Mission which reviewed the work progress of the barrage on Thursday, led by WB practice manager Mr Josses Mugabi.

Briefing the mission on the occasion, Sukkur Barrage Chief Engineer Syed Sardar Ali Shah suggested that a trail gate without counter weight should be installed at the weir instead of the pocket before the flood season as “we can observe the operation of the trail gate without counter weight of 80 tonne to reduce the extra load on the barrage”.

Sindh Barrages Improvement Project (SBIP) Deputy Director Abdul Razak Memon said the provision of the trail gate for physical demonstration had already been kept in the scope of the rehabilitation and modernisation of the Sukkur Barrage contract.

Ms Liyanage, who is also co-task team leader of the WB, said that it had been observed that the progress of the work of Sukkur barrage was continued according to the proper schedule.

She advised that there was also need to improve the health, safety environment.

Mr Mugabi said the methodology of the rehabilitation of Sukkur Barrage was organised, but it needed strengthening of the weaknesses.

He said that according to the suggestion and guidelines of a panel of experts and departments’ technical personnel and international consultants, the design work of the barrage was in progress.

The World Bank mission also visited the Indus Blind Dolphins Center, and ongoing construction works related to the SBIP, including the mechanical workshop and engineering works.

Those who accompanied the team included Coordination and Monitoring Unit of Planing and Development’s Project Coordi-nator Nazir Essani, Sociologist Ghulam Hyder Qureshi, Director Ghulam Murtaza Abro and others.

Published in Dawn, November 3rd, 2023

Opinion

Editorial

Iran’s new leader
Updated 10 Mar, 2026

Iran’s new leader

The position is the most powerful in Iran, bringing together clerical authority and political and ideological leadership.
National priorities
10 Mar, 2026

National priorities

EVEN as the country faces heightened risks of attacks from actual terrorists, an anti-terrorism court in Rawalpindi...
Silenced march
10 Mar, 2026

Silenced march

ON the eve of International Women’s Day, Islamabad Police detained dozens of Aurat March activists who had ...
War & deception
Updated 09 Mar, 2026

War & deception

While there is little doubt that Iran is involved in many of the retaliatory attacks, the facts raise suspicions that another player may be at work.
The witness box
09 Mar, 2026

The witness box

IT is often the fear of the courtroom and what may transpire therein that drives many victims of crime, especially...
Asylum applications
09 Mar, 2026

Asylum applications

BRITAIN’S tough immigration posture has again drawn attention to the sharp rise in asylum claims by Pakistani...