ISLAMABAD: The national grid operator — National Transmission & Despatch Company (NTDC) — issued notice of default to a Chinese firm for inordinate delays in the completion of a 45-km transmission line near Lahore.

In a notice of default, the NTDC has conveyed to Sin­o­hydro Corp Ltd that the scheduled completion for the 220kV transmission line was April 24, 2021 (ie 540 days from the effective date of Nov 1, 2019) which had lapsed a long time ago but the performance was still not up to the mark even after the delay of more than three years.

The NTDC said that the contractor had shown a non-serious attitude towards such an important project from the start of the project. “Even more than 41 months have lapsed since the commencement of the project but ‘you are not carrying out the contractual obligations including the site activities”.

This “situation is very alarming” and hence “a matter of grave concern”, said the NTDC, advising the contractor to take immediate remedial steps within 14 days of this notice to complete the project well in time. “Otherwise, the employer may terminate the contract forthwith by giving a notice of termination to the contractor” followed by encashment of performance guarantee.

The national grid operator reported that the transmission line is still far behind the revised completion schedule of May 2023.

The total material has not reached the site and civil works are not completed either as of now. The project is part of a larger $800 million financing from the Asian Development Bank.

Interestingly, despite the slow progress on a smaller project of a 220kV line of 45km in the plains, the NTDC has already awarded a contract to the same firm for a larger 765kV transmission line in one of the highest altitudes a couple of weeks ago – Lot-1 of Dasu to Mansehra segment for evacuation of power generation from Dasu Hydropower project.

Published in Dawn, March 18th, 2023

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Race against time
Updated 09 Feb, 2025

Race against time

While some bright spots emerged at Breathe Pakistan moot, we must streamline our climate governance.
Open door
09 Feb, 2025

Open door

THE door is still open for talks, National Assembly Speaker Ayaz Sadiq has reminded the PTI. What matters, however,...
Football suspension
09 Feb, 2025

Football suspension

ONCE again, Pakistan has been ousted from the global football family. FIFA recently suspended the Pakistan Football...
A year later
Updated 08 Feb, 2025

A year later

A war of egos has been fought between a handful of individuals at the cost of the well-being of millions of ordinary Pakistanis.
Wheat decision
08 Feb, 2025

Wheat decision

THE federal decision to stop setting the minimum support price for wheat and cease the staple’s procurement...
Dhanmondi attack
08 Feb, 2025

Dhanmondi attack

HISTORY has shown that unless states deliver development and equal rights to all, disenfranchised people can target...