Girders of Islamabad’s under-construction flyover collapse, days after deadly pillar fall

Published March 2, 2023
A screengrab from a CCTV video posted on social media of the girder collapse in Islamabad’s Bhara Kahu.—Twitter/@EngrTAadilHamid
A screengrab from a CCTV video posted on social media of the girder collapse in Islamabad’s Bhara Kahu.—Twitter/@EngrTAadilHamid

Girders of an under-construction flyover in the Bhara Kahu area of Islamabad collapsed on Thursday, less than a week after the bridge’s shuttering came apart leaving two labourers dead and three injured.

Islamabad police confirmed the incident in a tweet, adding that there were no injuries or casualties.

“The girders of an under-construction bridge have collapsed,” read a tweet by Islamabad Police.

It further said rescue and police personnel were on the site to ensure smooth traffic flow.

Unverified CCTV footage making the rounds on social media showed the massive concrete girders of the flyover tipping over, hitting another one before eventually caving in entirely, barely missing a pedestrian.

Capital Development Authority (CDA) Chairman Noorul Amin Mengal ordered an inquiry into the incident, state-run APP reported.

Speaking to reporters at the site, Amin said that the accident occurred due to a “crane slipping”. “The safety and health of the labourers cannot be compromised at any cost,” he added.

The IG Islamabad was also on site.

Second collapse in a week

On Feb 25, a pillar of the same bridge had fallen and killed two men, while injuring three others.

Talking to Dawn at the time, officials of the police and administration said it would be difficult for them to explain the cause of the incident as it required some technical expertise.

Prime Minister Shehbaz Sharif had taken the notice of the incident and sought a report from the CDA chairman.

Commissioner Islamabad Noorul Amin Mengal, who is also chairman of the Capital Development Authority (CDA), ordered an inquiry and constituted an eight-member committee at the time.

Mengal had claimed that during a preliminary investigation, it was revealed that there was a movement of two to three heavy trailers in early morning which hit the under-construction flyover.

The committee, under the supervision of the deputy commissioner, was constituted to investigate the incident and fix responsibility, the chief commissioner said, adding that legal action would be taken against those found responsible for the incident.

Prime Minister Shehbaz Sharif on September 30 had laid the foundation of the Bhara Kahu bypass and directed the National Logistics Cell (NLC) to complete the project within three months instead of four as mentioned in PC-I.

Editorial

Budget delay
Updated 04 Jun, 2026

Budget delay

With economic stabilisation yet to translate into tangible improvement in living standards, the country’s leaders are finding it increasingly difficult to ignore demands for relief.
Absentee lawmakers
04 Jun, 2026

Absentee lawmakers

TWENTY per cent. That is the percentage of lawmakers whose commitment to their vocation is reflected in the time ...
Deliberate provocations
Updated 04 Jun, 2026

Deliberate provocations

THE latest events at Al-Aqsa Mosque reflect the growing impunity with which extremist Israeli settlers operate. ...
Missing confidence
03 Jun, 2026

Missing confidence

For the government, the economy may be more stable now than it was three years ago, but for manufacturers and exporters, it is still difficult to do business.
GB elections
03 Jun, 2026

GB elections

THERE has been some heated politicking in the country’s scenic north in recent days, with Gilgit-Baltistan finally...
The Lebanon factor
03 Jun, 2026

The Lebanon factor

THE fragile calm that followed the recent US-Iran confrontation is being tested. Iran has made it clear that it does...