KARACHI: Chief Minister Syed Murad Ali Shah on Wednesday directed the local government department to complete a portion of 39-km-long Malir Expressway up to Quaidabad in the next eight months.

The chief minister chaired a meeting to review the pace of work on the expressway project.

He was informed that construction work on the Malir Expressway was in full swing and so far 15-km earth work right from Jam Sadiq Bridge to Quaidabad had been completed, but there were some land issues, which needed to be resolved.

The provincial government had envisaged a plan to construct an expressway on the Malir river to facilitate thousands of commuters and heavy traffic of Karachi Port, Korangi Industrial Area, Landhi Industrial Area, Steel Mills, Port Qasim and other such areas towards upcountry through the National and Superhighways.

The project includes the development of 38.75 kilometres 3x3 lane expressway with controlled access along the Malir river starting from Korangi Creek Avenue (DHA) and ending at Karachi-Hyderabad Motorway (M-9) near Kathore via the existing Link Road.

The proposed expressway will provide speedy access to main housing schemes along the route, reducing the commuting time from Korangi Creek Avenue (DHA) to Superhighway (M-9) to only 25 minutes. The Expressway will have six interchanges.

The progress concerning construction activities including clearing and grubbing on the main alignment and construction of temporary service roads for the movement of construction equipment inside the river bed is in full swing.

The meeting was informed that there were some land issues as some parts of the land were owned by private persons and some parts belonged to the Pakistan Air Force.

The chief minister directed the chief secretary to talk to the authorities concerned so that work on the project might continue unhindered.

He also directed the city police chief to set up a police picket at the site of the Malir Expressway for security of labourers and machinery mobilised there.

The chief minister directed the local government department to keep visiting the work going on the expressway so that its portion up to Quaidabad could be completed within the next eight months.

Published in Dawn, April 21st, 2022

Opinion

Editorial

A new deal
Updated 16 Jun, 2026

A new deal

AFTER three and a half months of war between US-Israel and Iran and an acrimonious temporary ceasefire, a genuine...
Charter of economy
16 Jun, 2026

Charter of economy

NO one expected the PTI to accept the government’s invitation to sign a charter of economy; just as few expected...
Hostage seamen
16 Jun, 2026

Hostage seamen

SOME 50 days on, 11 Pakistani nationals are still in Somali pirates’ captivity. Their appeals to the Pakistani and...
Climate choices
Updated 15 Jun, 2026

Climate choices

The country is confronting increasingly volatile weather patterns with consequences for agriculture, infrastructure, public health and economic planning.
Brief opening
15 Jun, 2026

Brief opening

WE have been here before. Throughout the weekend, there was great anticipation that a tentative framework for peace...
Environmental disaster
15 Jun, 2026

Environmental disaster

IT was a heartbreaking sight. A recent news report in these pages carried a picture of a sea turtle lying half ...