Pakistan's first HVDC transmission line passes testing

Published June 4, 2021
The formal operation of the Matiari-Lahore transmission line will begin on Sept 1. — Photo courtesy Wikimedia Commons/File
The formal operation of the Matiari-Lahore transmission line will begin on Sept 1. — Photo courtesy Wikimedia Commons/File

LAHORE: Testing for the evacuation, transmission, dispatch and distribution of 2,200MW of electricity by the country’s first high voltage direct current (HVDC) Matiari-Lahore transmission line was successfully carried out on Thursday, paving the way for the launch of the line’s formal operation on Sept 1, a revised date for the commercial operation of the mega project being completed under the China-Pakistan Economic Corridor (CPEC).

“Since the line has been designed to evacuate 4,000MW from the power plants in south (Sindh) in alternative current (AC) mode, convert it in direct current (DC) at a convertor station at Matiari (Sindh, near Hyderabad), transport/transmit it in DC mode and dispatch it to the distribution systems of the power distribution companies after converting it from AC to DC at a convertor station near Bhai Pheru (Lahore), the transmission and despatch test of 2,200MW is a major test ahead of the commercial operation of the line set for Sept 1,” a spokesman for NTDC told Dawn.

He said the 660kV HVDC line is new technology in Pakistan being completed under the ‘build, own, operate and transfer basis by the Matiari-Lahore Transmission Company under the supervision of the NTDC. From Sept 1, the official said the line would start evacuating, transmitting and dispatching of 4,000MW to the urban load centres in central and northern parts of the country.

“After 25 years operation, the project will be handed over to the NTDC,” he said.

In April, this year, the decision for the launch of commercial operation of the line from Sept 1 had been taken after various technical and contractual issues were amicably resolved between the Pak Matiari-Lahore Transmission Company Limited (PMLTCPL) and the NTDC.

The project agreements were signed between the NTDC and the PMLTCPL at the PM house on May 14, 2018, and its construction was launched in December 2018. Currently, the construction of the project is almost complete and the project is at advanced stages of testing and commissioning, and more than 95pc testing and commissioning stands completed.

Published in Dawn, June 4th, 2021

Opinion

Editorial

Judiciary’s SOS
28 Mar, 2024

Judiciary’s SOS

SOME clearly thought that senior judges would prove just as easily ‘manageable’ as our seasoned politicians...
Data protection
28 Mar, 2024

Data protection

WHAT do we want? Data protection laws. When do we want them? Immediately. Without delay, if we are to prevent ...
Selling humans
28 Mar, 2024

Selling humans

HUMAN traders feed off economic distress; they peddle promises of a better life to the impoverished who, mired in...
New terror wave
Updated 27 Mar, 2024

New terror wave

The time has come for decisive government action against militancy.
Development costs
27 Mar, 2024

Development costs

A HEFTY escalation of 30pc in the cost of ongoing federal development schemes is one of the many decisions where the...
Aitchison controversy
Updated 27 Mar, 2024

Aitchison controversy

It is hoped that higher authorities realise that politics and nepotism have no place in schools.