ISLAMABAD: The Auditor General of Pakistan has observed that the World Bank-assisted ‘Sindh Water Sector Improvement Project’ aimed at improving the efficiency and effectiveness of irrigation water distribution in area water boards of Ghotki, Nara and Left Bank, is at low performance that will ultimately affect the overall performance and achievement of the project.

Key findings of the audit report of the project for the financial year 2018-19, show non-production of record and vouchers, misstatement in use of vehicles, non-recovery of sales tax on services, unauthorised re-appropriation of funds, non-achievement of PC-1 targets, unauthorised regularisation of staff, non-submission of adjustment account, excess drawl of salaries over PC-1 provision, incurrence of expenditure on activities beyond the scope of the project, drawl of loan from AWB and non-transparent hiring of staff.

Pointing out the key issue for the future, the audit report says “the project is going to slow on its pace and has missed its target especially over the component “community development and capacity building” where the targets for the creation of desired number of farmer organisations and construction of dams is yet to achieve”.

The lapses on part of department indicate improper watch and absence of internal controls. The audit mainly recommends that causes of deviations from rules and procedures may be justified, recoveries as pointed out be made and the irregular expenditure may be regularised besides internal controls may also be strengthened to achieve the intended purposes.

The audit report pointed out that while reviewing the records of the project director of Sindh Water Sector Improvement Programme in Hyderabad for the year 2018-19, it was observed that an expenditure of Rs26.457 million was incurred for various purposes, however, relevant vouchers and payments details were not provided.

Published in Dawn, February 5th, 2020

Opinion

Editorial

Sustainable path?
Updated 13 Jun, 2026

Sustainable path?

The FY27 budget is the first clear signal that the government is ready to transition from stabilisation to growth.
Prioritising education
13 Jun, 2026

Prioritising education

THOUGH the improvement in the country’s literacy rate may be slight, as highlighted by the Economic Survey, it ...
Poverty’s rise
13 Jun, 2026

Poverty’s rise

AS attention turns to the government’s plans for the coming fiscal year, one set of figures deserves particular...
A difficult story
Updated 12 Jun, 2026

A difficult story

Unless productivity becomes the dominant target of economic policy, Pakistan will continue to oscillate between crises and fragile recovery.
Rough waters
12 Jun, 2026

Rough waters

AMONGST the key potential triggers for fresh conflict in South Asia is water. The Indian state is behaving in an...
Politicised football
12 Jun, 2026

Politicised football

ALMOST three-and-half years since Lionel Messi led Argentina to FIFA World Cup glory, the latest edition of...