20,000 workers booked for abetting in power theft

Published December 28, 2018
Rs150m has been recovered from electricity defaulters over past six months, Senate panel told. — File photo
Rs150m has been recovered from electricity defaulters over past six months, Senate panel told. — File photo

ISLAMABAD: The Senate Standing Committee on Power was informed here on Thursday that cases against around 20,000 employees belonging to several electricity distribution companies had been filed for abetting in power theft.

The committee, chaired by Senator Fida Muham­mad, was also informed by special secretary of power division Hassan Nasir Jami that delays were being faced by the power division in taking action against these employees because of slow action by distribution companies.

The committee was informed that Rs150 million had been recovered from electricity defaulters over the past six months.

Rs150m has been recovered from electricity defaulters over past six months, Senate panel told

Officials of distribution companies told the committee of their problems in carrying out instructions of the power division. Senior officials of the Lahore Electric Supply Company [Lesco] said that a case had been filed against a local steel mill owner for electricity theft of over Rs110 million.

However, even after the vacation of the LHC stay taken by the owner of the steel mill, the Punjab police were still reluctant to take action and arrest owners of the steel mills.

The committee was further informed that a comprehensive plan was being prepared by the power division and electricity distribution companies to reduce cases of power theft.

When members of the committee asked why electricity for up to 12 hours was being provided to feeders with high number of cases of power theft, the officials concerned informed the committee that policy decisions were made by the federal cabinet, but when members of the committee pressed further for more details, it was revealed by the officials that the power division had failed to forward the summary to the federal cabinet in this regard.

The committee directed the power division to forward the summary to the Cabinet Committee on Energy that electricity supply should be limited to only two hours a day to areas that fell in high theft feeders.

Senator Noman Wazir demanded that plans being prepared to reduce electricity theft should be realistic and financially viable for consumers.

The committee was informed that the Peshawar Electric Supply Company [Pesco] had been granted permission to conduct a survey for laying 3,000 kilometres of smart cables, while smart cables and digital meters were also being installed in Lesco and the Islamabad Electric Supply Company [Iesco].

Published in Dawn, December 28th, 2018

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Energy inflation
Updated 23 May, 2024

Energy inflation

The widening gap between the haves and have-nots is already tearing apart Pakistan’s social fabric.
Culture of violence
23 May, 2024

Culture of violence

WHILE political differences are part of the democratic process, there can be no justification for such disagreements...
Flooding threats
23 May, 2024

Flooding threats

WITH temperatures in GB and KP forecasted to be four to six degrees higher than normal this week, the threat of...
Bulldozed bill
Updated 22 May, 2024

Bulldozed bill

Where once the party was championing the people and their voices, it is now devising new means to silence them.
Out of the abyss
22 May, 2024

Out of the abyss

ENFORCED disappearances remain a persistent blight on fundamental human rights in the country. Recent exchanges...
Holding Israel accountable
22 May, 2024

Holding Israel accountable

ALTHOUGH the International Criminal Court’s prosecutor wants arrest warrants to be issued for Israel’s prime...