Another Golen Gol power unit linked to national grid

Published
15

LAHORE: The Water and Power Development Authority (Wapda) has synchronised a second unit of the 108MW Golen Gol hydropower project and connected it to the national grid through the most crucial transmission line it laid from Chitral to Timergara.

“We have successfully synchronised the second unit of 36MW and adding the power to the national grid after evacuating it through completion of the most crucial transmission line from Golen Gol (Chitral) to Timergara,” Wapda Chairman retired Lt Gen Muzammil Hussain told Dawn.

The 180-kilometre-long Golen Gol-Timergara transmission line passes through the most difficult mountainous terrain having extreme weather conditions. As many as 706 transmission towers, including 141 towers of 132kV and 565 towers of 220kV, have been erected on the snow-clad mountain peaks, including that of Lowari Top at the highest altitude of 10,312 feet. Transmission towers in Pakistan have never been erected at this altitude.

706 transmission towers, including 141 towers of 132kV and 565 of 220kV, have been erected on snow-clad mountains

“Since the first unit of the project had started power generation in January this year, providing electricity to Chitral, upper Chitral and Darosh more than their need, synchronisation of the project’s second unit and evacuation of power through transmission line is big news for the nation. Soon the project’s third unit will also be synchronised,” the Wapda chief said.

Although construction of transmission lines does not fall within the ambit of Wapda after unbundling of its power wing way back in 2007, it took the construction of transmission line for Golen Gol project as a challenge. It not only completed the task on its own but also successfully energised the said transmission line two days ago.

The project has now been connected to the national grid. Thus, the project has started providing electricity to the system through its second unit on a trial basis via the national grid. “The second unit is being operated on various loads in accordance with the standard operating procedure (SOP) up to its maximum generation capacity of 36MW,” said a spokesperson for Wapda in a press release issued on Sunday.

He said the first unit had been providing electricity to Chitral and its adjoining areas since its commissioning in January through a local arrangement developed by Wapda.

“The project, since its commissioning, has provided more than 33 million units of electricity to consumers. The third and last unit of the project is also complete. The wet commissioning of third unit will commence very soon by connecting it to the national grid,” he explained.

The project has been constructed on Golen Gol — a tributary of River Mastuj near Chitral — in phases. The project will provide 436 million units of electricity to the national grid every year. The project is expected to save around Rs3.7 billion per annum.

Published in Dawn, September 24th, 2018

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Expanding conflict
31 Jul, 2026

Expanding conflict

WITH neither of the belligerents willing to back down, and the theatre of conflict expanding geographically, the...
Spoils and spats
31 Jul, 2026

Spoils and spats

A FIGHT over assembly seats in Azad Jammu and Kashmir has laid bare what seem to be some deep resentments between ...
Unfair tax system
31 Jul, 2026

Unfair tax system

THE disclosure that the FBR collected nearly Rs1.9tr in sales and income taxes through electricity bills over the...
Debt that stays
30 Jul, 2026

Debt that stays

THE power sector’s circular debt grew by Rs61bn in the last fiscal year, taking the total to roughly Rs1.67tr from...
HIV warning
30 Jul, 2026

HIV warning

THE HIV infections detected around two SESSI-run hospitals in Karachi demand far more than another hurried committee...
End trafficking
30 Jul, 2026

End trafficking

MODERN slavery, in the form of human trafficking, is among the state’s gravest failures. Scores of Pakistanis are...