Inflatable rubber dams

Published
6

THE irrigation department of Punjab has come up with a proposal of introducing inflatable rubber dams for the eastern rivers in the province to serve not only as small water storages, but also, improve the biodiversity of the area which was degraded owing to drying up of the waterways as a result of the Indus Water Treaty 1960.

The irrigation department has so far identified eight points — four each at Sutlej and Ravi rivers — for the construction of these proposed rubber dams.

The feasibility study and a detailed design for the pilot project in Bahawalpur district has been prepared by The Project Implementation Consultants — a joint venture of Messrs ACE, Nespak and SMEC.

“In fact, the consultants have studied three sites — one on the Ravi (Okara-Faisalabad bridge) and two on the Sutlej (Bahawalpur-Lodhran Road bridge and Bahawalpur N-5 bridge).

But the Bahawalpur-Lodhran Road bridge on River Sutlej has been selected for the construction of the first such facility, keeping in view the socio-political acceptability considerations, according to an official of the irrigation department, involved with the project’s planning.

This idea is in vogue in developed nations like the USA, Canada, Italy and Spain and developing states like China, India and Bangladesh. China boasts over 2,000 rubber dams, while Bangladesh has built several dozens of them so far.

“The inflatable dams are a good option during low flow as well as high floods. For in case of flood, the rubber weir may be deflated within hours to allow the strong current to pass through the channel while a concrete weir will be washed away”

“Currently, the proposal is lying with the donors, both the provincial government as well as the world agencies interested in lending for water projects, to seek funds for its implementation.”

The inflatable rubber dams are rubber-coated cylindrical fabrics placed across water channels, fixed to concrete foundation by bars and anchorage bolts, to raise the upstream water for irrigation, flood control or other uses. Air, water or a combination of both are used to inflate the tubes.

In the proposed Bahawalpur Bridge project, a 2.5 metres high and 155.3 metres long inflatable weir will be installed on top of the spillway which is divided into four bays, the official says, adding, it will create an approximately 13km-long lake upstream at a cost of around Rs3bn.

The cost includes the compensation amount to be paid to the owners of the land within the main creek of River Sutlej. The construction period will span over 18 months.

Besides serving as a water storage dam for irrigation purposes, it will also help recharge ground water aquifer and improve availability of water for drinking purpose in the project impact area.

Coupled with enhanced availability of tubewell irrigation due to recharged aquifer, it will help in improved crop yields and generate agro-economic benefits, the official says.

The 13km lake can also be used for fish farming as well as for recreational activities like boating, while its impact on biodiversity of the area will also be significant, he said, pointing out the additional benefits of the plan, adding, “Consequent upon the success of the pilot project, a series of similar projects will be replicated in the remaining reaches of Sutlej and Ravi rivers.”

A technical member of the project team says mechanical equipment of the rubber dam, including auto deflation system, air compressor for activating pneumatic valves, air blowers and control panels, will be housed in a four-story building.

The official says that initially construction points on the rivers have been identified where concrete foundations or platforms are already available in the form of bridges to keep the costs low.

About the strength and reliability of the fabric used, he says, “It could sustain knife cuts and has a life span of over two decades.”

A consultant of the water and power authority (requesting anonymity) supported the rubber dam proposal saying, “The technology may be used to build small reservoirs to meet the needs of the impact area, while it entails no damages in any respect.

The inflatable dams are a good option during low flow as well as high floods. For in case of flood, the rubber weir may be deflated within hours to allow the strong current to pass through the channel while a concrete weir will be washed away.”

Former Chairman Wapda, Engineer Shamsul Mulk, said he can give his professional opinion on the proposal only after going through its feasibility study but stressed that ‘known technologies’ should be preferred for the development of water reservoirs.

Published in Dawn, The Business and Finance Weekly, June 19th, 2017

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...
Terror and politics
Updated 29 Sep, 2026

Terror and politics

There is an urgent need to tone down the rhetoric and tackle terrorism as a collective challenge for both the affected provinces and the federation.
Watching the glaciers
29 Sep, 2026

Watching the glaciers

THE latest signs from Pakistan’s mountains are worrying. Suparco says the number of unfrozen glacial lakes it...
Dangerous agenda
29 Sep, 2026

Dangerous agenda

AS the world remains fixated on the US-Iran conflict, elsewhere in the Middle East, Israel is consolidating its grip...