525MW Nandipur power plant starts test run

Published
30

LAHORE: The government has started running the 525-megawatt Nandipur power plant on trial basis after it was finally converted to Regasified Liquefied Natural Gas (RLNG).

“The Nandipur thermal power plant has been converted to gas. And the officials concerned have launched a test run after we started providing gas to it from Thursday,” Sui Northern Gas Pipelines Limited (SNGPL) Managing Director (MD) Amjad Latif told Dawn on Saturday.

“Since the plant is running on trial basis, we are providing 10 to 30MMCFD of RLNG to it according to demand. And once the plant’s commercial operation starts, its total demand will be 100MMCFD,” the MD explained.

When questioned regarding suspension of various power plants, including 412MW Rousch in Khanewal district due to shortage of gas, the SNGPL chief claimed that none of the plants was closed due to a shortage.

“We have sufficient gas. Some of the plants, including Rousch, are on scheduled outages. And once they demand after ending the scheduled outages, we will surely provide them gas,” he added.

He said the SNGPL had laid a new and dedicated pipeline for provision of RLNG to Nandipur plant.

Since being commissioned a few years ago, the Nandipur plan could not be run properly due to technical and procedural flaws. Though the government continued claiming the project would be a success, it attracted severe criticism from opposition parties and technical experts on various issues. Following frequent technical, procedural and administrative problems, the government finally removed its project director.

The Ministry of Water and Power was also reported to have identified three major technical and procedural problems with the project and sought action against those responsible. The selection of low-capacity furnace oil treatment plant for such a big project, flaws in the long-term outsourcing of operation and maintenance contract and awarding the contract to engineering, procurement and construction contractors on a short-term basis were the key shortcomings that led to failure of the project.

Moreover, poor quality fuel believed to have been adulterated on its way to Nandipur from Karachi had also caused initial problems.

Petroleum Minister Shahid Khaqan Abbasi was also reported to have claimed that there would be no technical problem with the 525MW plant if it was run on natural gas. He opposed the selection of dual fuel combined cycle technology for the project on technical grounds, but was overruled when a high-level meeting was informed that banks were not ready to extend funds unless the plant had alternative fuel.

Published in Dawn, April 23rd, 2017

Opinion

Editorial

Maritime alliance
Updated 01 Aug, 2026

Maritime alliance

AS the US-Iran war drags on, new battle lines are being drawn. The pro-US Gulf Arab monarchies and Iran have enjoyed...
Local governance
01 Aug, 2026

Local governance

INTERIOR Minister Mohsin Naqvi’s speech at a business summit on Thursday has stirred a hornet’s nest. His...
Murders in Balochistan
01 Aug, 2026

Murders in Balochistan

GOOD news is scarce in Balochistan. Seven labourers were abducted and gunned down in Turbat city recently. Four...
Expanding conflict
31 Jul, 2026

Expanding conflict

WITH neither of the belligerents willing to back down, and the theatre of conflict expanding geographically, the...
Spoils and spats
31 Jul, 2026

Spoils and spats

A FIGHT over assembly seats in Azad Jammu and Kashmir has laid bare what seem to be some deep resentments between ...
Unfair tax system
31 Jul, 2026

Unfair tax system

THE disclosure that the FBR collected nearly Rs1.9tr in sales and income taxes through electricity bills over the...