LAHORE: The progress on Neelum-Jhelum Hydro Project stands at 78.5 per cent, and the tunnel boring machines (TBM), which suffered rock burst on May 31 last year, were restored in the second week of January.

Chief Executive Officer Engineer Muhammad Zubair told the Wapda chairman during a visit to the site on Friday. Chairman Zafar Mahmood asked the project authorities to further expedite their efforts to meet the revised schedule.

As per revised schedule, first generating unit of the project is expected to be completed in July 2017, whereas the remaining three units will come on line by the end of 2017 in different phases.

Speaking on the occasion, the chairman appreciated the commitment and devotion of the project authorities in implementing this extremely precarious project. He said that most of the critical targets relating to construction of the project had been successfully achieved, therefore, Wapda was confident to complete it as per the timelines.

During the visit, the chairman also witnessed excavation of tunnel through the TBM at rock burst site. The chief executive officer apprised the chairman that both TBMs deployed at the project had been functioning satisfactorily. He further informed the chairman that installation of three hydraulic gates at the dam site (Nauseri, Neelum Valley) shall be completed by 15 March 2016..

The Neelum Jhelum Hydropower Company is constructing a world class underground power generation facility. The project envisages 90 per cent construction work under high mountainous overburden and only 10 per cent above the surface.

The project, on its completion, will contribute 5.15 billion units of low-cost and environment friendly electricity to the national grid.

Published in Dawn, March 12th, 2016

Opinion

Budgeting without people

Budgeting without people

Even though the economy is a critical issue, discussions about it involve a select few who are not really interested in communicating with the people.

Editorial

Iranian tragedy
Updated 21 May, 2024

Iranian tragedy

Due to Iran’s regional and geopolitical influence, the world will be watching the power transition carefully.
Circular debt woes
21 May, 2024

Circular debt woes

THE alleged corruption and ineptitude of the country’s power bureaucracy is proving very costly. New official data...
Reproductive health
21 May, 2024

Reproductive health

IT is naïve to imagine that reproductive healthcare counts in Pakistan, where women from low-income groups and ...
Wheat price crash
Updated 20 May, 2024

Wheat price crash

What the government has done to Punjab’s smallholder wheat growers by staying out of the market amid crashing prices is deplorable.
Afghan corruption
20 May, 2024

Afghan corruption

AMONGST the reasons that the Afghan Taliban marched into Kabul in August 2021 without any resistance to speak of ...
Volleyball triumph
20 May, 2024

Volleyball triumph

IN the last week, while Pakistan’s cricket team savoured a come-from-behind T20 series victory against Ireland,...